Bart Reines Luxury Homes
186 Bal Bay DriveLive Project Dashboard
← Proposal
Master Project Tracker Crown Estate Management
OAC #5 — May 27, 2026  ·  Next OAC: June 3, 2026 at 11:00 AM
Contract Sum
$19,280,943
Total GC contract value
Completion
65%
Of total scope, as of OAC #5
Current Pay App
#18 — May 19, 2026
Most recent draw application
Current Draw
$484,582
This pay-app period
Balance to Complete
~$7,020,000
Remaining contract value
Owner Target
Feb 28, 2027
Substantial completion goal

⚠ Critical Items — OAC #5

Veneer approval
TIME CRITICAL — must approve before June 15 Royal Laser 2F delivery
Gas rough inspection
TODAY 5/27 — if pass, call 1F framing inspection
Back deck structural
Contested between Omar/BRLH — Manuel coming this week
FPL Easement
Michael to retrieve from Marty @ 188 marina → notarize → submit county
Interior louvers
Borges comments on Victor's shop drawings still pending
Schedule variance: BRLH schedule Aug–Dec 2027 (5–10 month gap — unresolved)

This dashboard is the live operating picture for 186 Bal Bay Drive — the same tracker used by the contractor's PM, the site superintendent, and the owner's representative to run the project. It consolidates the OAC meeting record, the critical-task register, the city inspection log, owner decisions, subcontractor buyout, the field control board, and the master schedule into one view. Use the tabs above to move between them; the search box filters the active tab.

Critical Task Register

# Category Task Owner Status Due Source Notes
1.0 ✅ RESOLVED Gas revision — Andres email approved 5/6, hard copies to follow Andres ✅ APPROVED 5/6 5/6/2026 OAC2 CRITICAL MILESTONE. Gas revision was the master blocker. Walls can now proceed to close on 2nd floor. 2 signed/sealed hard copies still needed for city submission.
2.0 ✅ RESOLVED HVAC pre-drywall walk — completed 5/6 with Gabriel Greg/Omar ✅ DONE 5/6 5/6/2026 Task List + OAC2 Walk complete. New punch list from walkthrough: bed 1 drain, access panels, VIP filter slot, bed 2 damper filter racks. Omar working remaining items.
3.0 ✅ RESOLVED Framing inspection — passed (except staff/service wing) Omar ✅ PASSED (partial) Prior Inspections sheet Passed except Staff Area/Service Wing. Service wing needs correction.
4.0 ✅ RESOLVED Inspector Valente — met, BNI engineer letter in progress Omar/Greg ✅ MET 5/4/2026 Task List Met with inspector. Recall inspection of front stairs + at-grade landing slab needed. Omar getting BNI structural engineer letter.
5.0 ✅ RESOLVED Condensate lines — horizontal insulation materials arrived 5/1 Omar/Gabriel ✅ Materials on site 5/1/2026 Task List Materials arrived 5/1. Omar making Gabriel insulate horizontal condensate lines.
6.0 ✅ RESOLVED Remote AC sensors — locations given to Gabriel at 5/6 walkthrough Greg/Omar ✅ DONE 5/6/2026 Task List Locations given to Gabriel at walkthrough. Gabriel will install.
7.0 ✅ RESOLVED All fresh air dampers — Gabriel confirmed installed and working 5/6 Gabriel ✅ CONFIRMED 5/6/2026 Task List Confirmed with Gabriel at walkthrough.
8.0 ✅ RESOLVED German — exterior sconce locations marked outside massage balcony Greg/Omar ✅ DONE (low one pending) 5/6/2026 Task List Done except low one on side of walkway.
9.0 ✅ RESOLVED Return for guest bed 1 from corridor — Tony PE approved, in progress Omar ✅ In Progress ASAP Task List Tony approved. Omar in progress. Also needs to draw from hallway plenum per Craig.
10.0 🔴 CRITICAL Wellness Center HVAC — upsize to 3 ton, new condenser (DECIDE 5/13) Greg/Andres Open — Awaiting Calcs 5/13/2026 OAC2 Existing 1.5 ton vs ~33K BTU load. New condenser + MEP revision required. Tony + Vlad running calculations. Keep ceiling open.
11.0 🔴 CRITICAL Gas revision hard copies — 2 signed/sealed to city Andres Open ASAP OAC2 Email approved 5/6. City still needs 2 signed and sealed hard copies submitted.
12.0 🔴 CRITICAL Roof HVAC isolators — David Rogers draft → Gabriel review → BNI stamp → city Chana/Greg In Progress ASAP OAC2 Chana reviewing draft with Gabriel. Then BNI stamp. Then process with city.
13.0 🔴 CRITICAL His & Hers stone — Bart needs area list for shop drawings Chana Open ASAP Task List Bart wants list of which bathrooms get stone first to start shop drawings. Chana to make 2nd floor slab area list and email Bart + Greg.
14.0 🔴 CRITICAL Interior painting — offer Harold $100K flat (Alex confirmed) Greg/Chana Open — Action Required ASAP OAC2 + Alex 5/4 Leveling doc to ownership this week. Harold ~$10K cheaper, fewer COs. If declined: remove closets or third bid.
15.0 🔴 CRITICAL Front stairs — recall inspection, BNI engineer letter Omar Open ASAP Task List Inspector Valente needs evidence. Omar getting BNI structural engineer letter.
16.0 🔴 CRITICAL Floor boxes — eliminate wellness boxes pending MEP revision Greg/Chana Partial Approval ASAP OAC2 5/6 Approved by Alex except wellness room. Cannot finalize until wellness MEP revision done.
17.0 🔴 CRITICAL Wellness center MEP revision (240V? No hyperbaric?) Andres/Tony Open 5/13/2026 OAC1 + OAC2 MEP revision required for wellness room electrical. Andres following up with Tony. Vlad comments 5/6.
18.0 🔴 CRITICAL HVAC Gabriel punch list from 5/6 walk — 4 items Gabriel/Omar Open 5/13/2026 Task List walkthrough results 1) Bed 1 drain blocking filter 2) Relocate access panels bed 1 & 3 3) VIP suite filter slot (Victor) 4) Bed 2 damper blocking filter racks — Victor to change all ceiling AHU filter racks.
19.0 🔴 CRITICAL Bed 3 service wing framing — failed inspection, correction needed Omar Open ASAP Inspections sheet Framing inspection passed except staff/service wing. Correct and recall.
20.0 🔴 CRITICAL P&P Plumbing — demand letter still required Greg/Chana Open ASAP Omar control board Pattern documented. Demand letter required per Omar's board. No resolution shown in Gregg's tracker.
21.0 🟠 HIGH Carousel mock-up — 5/7 at 2pm (Victor bending metal bar) Greg/Victor/Paul Scheduled 5/7/2026 OAC2 Brass inlay edge detail + deflection assessment with black tile. Paul (Argent) reviewing. Written confirmation of pricing + credit needed.
22.0 🟠 HIGH 2nd floor soffit alignment issues — site walk 5/7 Omar/Greg Scheduled 5/7/2026 OAC2 Owner videos flagged misalignments. Resolve during site walk. Document corrective actions.
23.0 🟠 HIGH Borges on site 5/7 to discuss facade metals with Omar Andres/Omar Scheduled 5/7/2026 OAC2 Brake metal: Andres sent marked-up shop drawings 5/6 evening. Victor to site measure + samples. Alex color approval needed.
24.0 🟠 HIGH Landscape — Matthew on site 5/7, 2 signed/sealed copies for city Greg Scheduled 5/7/2026 OAC2 Matthew bringing plans for city processing.
25.0 🟠 HIGH Metal fencing — hidden areas to pickets, decorative at visible, add screens Greg/Victor Open 5/13/2026 OAC2 Marked drawings needed: decorative vs picket by location. Also add privacy screens for garage electrical panels + exterior water heaters + Jandy panels.
26.0 🟠 HIGH Civil engineer Marco — Omar sketch to reduce fees Omar/Greg In Progress 5/13/2026 OAC2 Gregg spoke to Marco. Omar sending sketch to reduce scope/fees.
27.0 🟠 HIGH Safe room doors — written quote, pick certified installer Chana Open ASAP OAC1 + OAC2 Will come back with quotes per OAC2. Must pick installer before safe room door supplier can make shop drawings.
28.0 🟠 HIGH Royal Laser — phased delivery discussion, Alex watching Chana Open ASAP Task List Alex asking for delivery target date. Chana to contact Greg Orsini (Royal Laser) about phased delivery.
29.0 🟠 HIGH Tub filler + drain — her master bath, core drill + rough Omar/Plumber Open ASAP Task List Omar to core drill. Plumber installs rough in floor.
30.0 🟠 HIGH Anti-scalding valve — her master bath (inspector requires) Chana/Plumber Open ASAP Task List Chana sending detail. Plumber will find spot after rough is in floor.
31.0 🟠 HIGH Freon lines master mech closet — lower (told Gabriel at 5/6 walk) Gabriel/Omar Open ASAP Task List Told Gabriel at walkthrough. Follow up to confirm.
32.0 🟠 HIGH Seal access panel back of elevator shaft Omar Open ASAP Task List Omar ordering panel that seals/locks. Confirm lock with Chana before ordering.
33.0 🟠 HIGH German (ELD) — 1st floor walk scheduled 5/20 Greg/Omar Scheduled 5/20/2026 Task List After German completes 2nd floor. Omar meets German for 1st floor schedule.
34.0 🟠 HIGH Gabriel — 1st floor HVAC walk scheduled 5/20 Greg/Omar Scheduled 5/20/2026 Task List Coordinate with 1st floor electrical walk.
35.0 🟠 HIGH Stair ceiling mirror — rosette detail, drawings from Arquitek in Procore Andres/Greg Open 5/13/2026 OAC2 Wood rosette to conceal chandelier lift. Millworker wood frame + separate mirror vendor. Latest drawings from Arquitek in Procore.
36.0 🟠 HIGH NWF — gym floor proposal owed Chana Open ASAP Task List NWF owes gym floor proposal. Chana to follow up.
37.0 🟠 HIGH File front door — PVT to provide NOA Chana Open ASAP Task List NOA needed for permit.
38.0 🟠 HIGH File garage door — NOA from John Buck, then complete inspection Chana Open ASAP Task List Get NOA then finish inspection.
39.0 🟠 HIGH Shearwall — pedestals shop drawing for exterior wood deck Chana/Greg In Progress ASAP Task List Comments sent 5/1. Shop drawing needed for pedestals.
40.0 📅 SCHEDULE New schedule — after 2F drywall + stone coordination Greg/Omar/Chana Open After drywall progress OAC2 5/6 Greg/Omar/Chana to build new schedule after completing 2F drywall and coordinating flooring install on 2F.
41.0 📅 SCHEDULE Next OAC — 5/13/2026 at 12:00 PM or 12:30 PM All Scheduled 5/13/2026 OAC2 Proposed time change from 1:30pm to noon or 12:30.
NEW 🟠 HIGH Camera payment — BRLH to pay, not CEM Greg Open ASAP Omar control board / Michael Omar's board notes 'Michael → cameras.' CORRECTION: cameras are BRLH's expense. Gregg to confirm with BRLH office/accounting. Michael has no payment obligation here.
NEW 🟠 HIGH Pool equipment payment — through Cinthia at BRLH accounting Gregg / Cinthia Open ASAP Michael update 5/6 Pool contractor approved. All equipment payments to be processed through Cinthia (BRLH accounting). Not a CEM action item.
NEW 🟠 HIGH Epoxy coating samples — acquire and have on site for owner review Greg Open 5/13/2026 OAC 5/6 + Michael update Engage Premier or specialist. Obtain epoxy floor coating samples for garage. Owner must review samples on site before decision. Coordinate with Argent walkthrough on garage cabinetry.
NEW 🟠 HIGH Jib doors for AC mech closets — Gregg to review Lujo product + pricing Greg Open 5/13/2026 Michael update 5/6 Two jib doors: one inside chef's kitchen AC mech closet, one just outside. These are BASIC (non-custom) doors now in the drywall scope — NOT Royal Laser millwork. Chana priced from Lujo. Gregg to review Lujo product and pricing.
NEW 🟠 HIGH AV Room HVAC — clarify exact equipment needed Greg Open 5/13/2026 Michael update 5/6 Gregg to determine exact equipment spec for AV room HVAC. Not a CEM item. Include in Gregg's tracker.
NEW 🟠 HIGH Royal Laser installer — Gregg + Omar + Alex to decide on site Gregg / Omar / Alex Open Next joint site visit Michael update 5/6 Gregg and Omar to discuss with Alex directly next time all three are on site. Decision: Russians as installer vs. BRLH sourcing another. Must be agreed in person — not via email or OAC.
NEW 🟠 HIGH Garage cabinetry decision — cover in Argent walkthrough Argent / Chana / Greg Open Next Argent visit OAC 5/6 + Michael update Determine in Argent walkthrough whether any garage cabinetry design is needed. Separately: Premier epoxy samples must be on site for owner review. Both items to be addressed together.
NEW 📋 INFO AGG Glass Contractors — gym glass wall shop drawings in progress Michael (CEM) / AGG Glass In Progress Post-drywall inspection Michael update 5/6 AGG Glass Contractors (Owner's contractor) handling gym glass wall. Initial shop drawings underway. Final measurements require finished wall, ceiling, and floor. Then fabrication. BRLH to ensure room completion is sequenced accordingly.
NEW 📋 INFO Shower enclosures / ribbed glass / mirrors — Katia + Chana + Greg Gregg / Chana Open TBD Michael update 5/6 CEM has no role. Assign to Gregg and Chana. RFPs sent to All Comp, Studio Glass, Champion Welding. BRLH to manage selection process.
5/13 ✅ RESOLVED Interior priming — APPROVED to start week of May 18 Gregg / Chana ✅ APPROVED 5/13 5/18/2026 OAC3 5/13 Decision made at OAC3. Painter to mobilize week of May 18.
5/13 ✅ RESOLVED Propane tank anti-flotation drawings — David Rogers completed Andres ✅ DRAWINGS COMPLETE 5/13/2026 OAC3 5/13 Stamped drawings ready. Now needs to be processed with city.
5/13 ✅ RESOLVED Main house transformer reorientation — REJECTED ✅ CLOSED 5/13/2026 OAC3 5/13 Too costly + FPL 8-foot clearance required. Orientation stays as-is.
5/13 🔴 CRITICAL Cryotherapy chamber — 230V vs 208V conflict, transformer noise, heat load Gregg / Tony Open — Researching Alt. 5/20/2026 OAC3 5/13 Cryofast unit requires 230V, house provides 208V. Noisy transformer required. 2-5kW heat load. Research 208V American units and split-unit options. Send Alex specs.
5/13 🔴 CRITICAL Deck & fire pit substructure — Manuel engineered drawings URGENT Manuel Open — Crew Waiting ASAP OAC3 5/13 Pedestals have no NOA. New plan: PT wood substructure by Manuel. Drawings are priority — crew will stop without them.
5/13 🔴 CRITICAL Drywall screw inspection — pass by end of week 5/11 Omar In Progress 5/14/2026 OAC3 5/13 Plumbers on site May 14 to complete so ceilings can close.
5/13 🔴 CRITICAL Facade/brake metal — color decision needed to proceed Andres / Victor Open — Color TBD 5/20/2026 OAC3 5/13 Victor's engineer reviewing fastening details. Color must be decided before shop drawings can be finalized.
5/13 🟠 HIGH City handrails — front steps + fire pit steps (new requirement) Andres Open 5/20/2026 OAC3 5/13 City courtesy walk resulted in minor handrail additions required. Andres to incorporate into fencing revision.
5/13 🟠 HIGH Roof fencing VE — white/less expensive alternative Andres / Victor In Progress 5/20/2026 OAC3 5/13 Ronaldo opposed black fencing on white roof. Alex concerned about appearance. Explore less expensive white solution. Andres to get VE marked-up drawings from Victor.
5/13 🟠 HIGH Landscape tree locations — conflict with underground utilities Gregg / Matthew Open 5/20/2026 OAC3 5/13 Trees on landscape plan conflict with underground utilities. Site walk needed with landscape architect.
5/13 🟠 HIGH SDS tile installer on site May 14 + Daniel starts May 15 Omar / Gregg Scheduled 5/14–5/15 OAC3 5/13 Exterior stone installer kickoff also May 15. Pool contractor job walk May 15.
5/13 🟠 HIGH Carousel — negotiate price + SDS installation method meeting May 14 Gregg / Chana In Progress 5/14/2026 OAC3 5/13 Brass inlays expected May 14. Meet SDS to approve installation method.
5/13 🟠 HIGH Noisy transformer — find insulated location, get specs from German Gregg / German Open 5/20/2026 OAC3 5/13 Possible cryo unit transformer described as 'jet engine' loud. Must find new location.
5/13 🟠 HIGH Argent — master carpet selection + bathroom 2 digital slab layout Paul / Argent Open 5/20/2026 OAC3 5/13 Paul to push Argent. Alex to be involved in carpet selection.
5/13 🟠 HIGH Electrician proposal for step-up transformer — get and review with Alex Gregg Open 5/20/2026 OAC3 5/13 Obtain electrician's proposal for transformer. Share with Alex for decision.
5/13 📅 SCHEDULE Next OAC — May 20, 2026 at 12:00 PM All Scheduled 5/20/2026 OAC3 5/13 Week of May 25 to be scheduled earlier for Alex.
5/18 ✅ RESOLVED Drywall screw inspection — 2ND FLOOR PASSED 5/18/2026 Omar / Lujo Drywall ✅ PASSED 5/18 5/18/2026 Daily Log 5/18 CRITICAL MILESTONE. Entire 2nd floor passed. Lujo adding 10 finishers 5/19. 1F drywall starts 5/19. Backing installation begins 1F.
5/18 🔴 CRITICAL P&P Plumbing — ABSENT 6 CONSECUTIVE DAYS (5/11–5/18). Demand letter NOW. Gregg / Chana Open — Demand Letter Required IMMEDIATE Manpower Log 5/18 Zero presence 5/11 through 5/18. Lujo starts 1F tomorrow. Condensate drains and tub/shower roughs must be done before ceilings close or they get drywalled in permanently.
5/18 🔴 CRITICAL SE Florida Mechanical — absent 5/13–5/18. HVAC punch items must clear before 1F ceiling closure. Gregg / Gabriel Open — Escalate IMMEDIATE Manpower Log 5/18 6 consecutive absences. HVAC punch list from 5/6 walk still open. Must clear before 1F ceilings close — bed 1 drain, access panels, VIP filter slot, bed 2 damper racks.
5/27 🔴 CRITICAL Veneer approval — TIME CRITICAL before June 15 Royal Laser 2F Paul / Alex / Argent Open — URGENT BEFORE 6/15 OAC5 Must approve: her closet, his & her vanities, massage vanity, cabana bar. June 15 is hard deadline.
5/27 🔴 CRITICAL Gas Rough Inspection — TODAY 5/27. Pass = call 1F Framing Omar / Andres Inspection Today 5/27/2026 OAC5 If gas passes today, call 1F framing inspection immediately.
5/27 🔴 CRITICAL Back deck structural / shearwall (Manuel) — contested Gregg / Manuel / BRLH Open — Contested This week OAC5 Omar says drawings show option; BRLH claims extra cost. Manuel coming this week.
5/27 🔴 CRITICAL FPL Easement — retrieve, notarize, submit Miami-Dade Michael (CEM) Open ASAP OAC5 Covenant at 188 marina (Marty). Must retrieve → notarize → submit to county before FPL relocates transformers.
5/27 🟠 HIGH Interior louvers — bottom detail unresolved Borges / Victor Open — site visit needed ASAP OAC5 Victor needs Borges comments. Borges wants site visit to finalize.
5/27 🟠 HIGH Gym glass wall header — scope active Gregg / AGG Glass In Progress TBD OAC5 AGG Glass (Owner's contractor) shop drawings in progress.
5/27 🟠 HIGH Luhho jib door specs — millwork sequencing Gregg In Progress TBD OAC5 Part of millwork sequencing. Gregg to confirm specs.
5/27 ✅ RESOLVED Sheet piles — wall gap closure APPROVED Gregg / Omar ✅ APPROVED 5/27 Done OAC5 Chana sent 5/26. Alex approved at OAC5.
5/27 ✅ RESOLVED Culligan water filtration — DECIDED Chana ✅ DECIDED 5/27 Done OAC5 Alex: RO to main kitchen faucet + $999 UV button upgrade.
5/27 ✅ RESOLVED Propane tank — delivered Chana ✅ RESOLVED Done OAC5 Delivery this week, no storage charge.
5/27 📅 SCHEDULE Next OAC — June 3, 2026 at 11:00 AM All Scheduled 6/3/2026 OAC5 Confirmed.
# Category Task Owner Status Due Source Notes
1.0 ✅ RESOLVED Gas revision — Andres email approved 5/6, hard copies to follow Andres ✅ APPROVED 5/6 5/6/2026 OAC2 CRITICAL MILESTONE. Gas revision was the master blocker. Walls can now proceed to close on 2nd floor. 2 signed/sealed hard copies still needed for city submission.
2.0 ✅ RESOLVED HVAC pre-drywall walk — completed 5/6 with Gabriel Greg/Omar ✅ DONE 5/6 5/6/2026 Task List + OAC2 Walk complete. New punch list from walkthrough: bed 1 drain, access panels, VIP filter slot, bed 2 damper filter racks. Omar working remaining items.
3.0 ✅ RESOLVED Framing inspection — passed (except staff/service wing) Omar ✅ PASSED (partial) Prior Inspections sheet Passed except Staff Area/Service Wing. Service wing needs correction.
4.0 ✅ RESOLVED Inspector Valente — met, BNI engineer letter in progress Omar/Greg ✅ MET 5/4/2026 Task List Met with inspector. Recall inspection of front stairs + at-grade landing slab needed. Omar getting BNI structural engineer letter.
5.0 ✅ RESOLVED Condensate lines — horizontal insulation materials arrived 5/1 Omar/Gabriel ✅ Materials on site 5/1/2026 Task List Materials arrived 5/1. Omar making Gabriel insulate horizontal condensate lines.
6.0 ✅ RESOLVED Remote AC sensors — locations given to Gabriel at 5/6 walkthrough Greg/Omar ✅ DONE 5/6/2026 Task List Locations given to Gabriel at walkthrough. Gabriel will install.
7.0 ✅ RESOLVED All fresh air dampers — Gabriel confirmed installed and working 5/6 Gabriel ✅ CONFIRMED 5/6/2026 Task List Confirmed with Gabriel at walkthrough.
8.0 ✅ RESOLVED German — exterior sconce locations marked outside massage balcony Greg/Omar ✅ DONE (low one pending) 5/6/2026 Task List Done except low one on side of walkway.
9.0 ✅ RESOLVED Return for guest bed 1 from corridor — Tony PE approved, in progress Omar ✅ In Progress ASAP Task List Tony approved. Omar in progress. Also needs to draw from hallway plenum per Craig.
10.0 🔴 CRITICAL Wellness Center HVAC — upsize to 3 ton, new condenser (DECIDE 5/13) Greg/Andres Open — Awaiting Calcs 5/13/2026 OAC2 Existing 1.5 ton vs ~33K BTU load. New condenser + MEP revision required. Tony + Vlad running calculations. Keep ceiling open.
11.0 🔴 CRITICAL Gas revision hard copies — 2 signed/sealed to city Andres Open ASAP OAC2 Email approved 5/6. City still needs 2 signed and sealed hard copies submitted.
12.0 🔴 CRITICAL Roof HVAC isolators — David Rogers draft → Gabriel review → BNI stamp → city Chana/Greg In Progress ASAP OAC2 Chana reviewing draft with Gabriel. Then BNI stamp. Then process with city.
13.0 🔴 CRITICAL His & Hers stone — Bart needs area list for shop drawings Chana Open ASAP Task List Bart wants list of which bathrooms get stone first to start shop drawings. Chana to make 2nd floor slab area list and email Bart + Greg.
14.0 🔴 CRITICAL Interior painting — offer Harold $100K flat (Alex confirmed) Greg/Chana Open — Action Required ASAP OAC2 + Alex 5/4 Leveling doc to ownership this week. Harold ~$10K cheaper, fewer COs. If declined: remove closets or third bid.
15.0 🔴 CRITICAL Front stairs — recall inspection, BNI engineer letter Omar Open ASAP Task List Inspector Valente needs evidence. Omar getting BNI structural engineer letter.
16.0 🔴 CRITICAL Floor boxes — eliminate wellness boxes pending MEP revision Greg/Chana Partial Approval ASAP OAC2 5/6 Approved by Alex except wellness room. Cannot finalize until wellness MEP revision done.
17.0 🔴 CRITICAL Wellness center MEP revision (240V? No hyperbaric?) Andres/Tony Open 5/13/2026 OAC1 + OAC2 MEP revision required for wellness room electrical. Andres following up with Tony. Vlad comments 5/6.
18.0 🔴 CRITICAL HVAC Gabriel punch list from 5/6 walk — 4 items Gabriel/Omar Open 5/13/2026 Task List walkthrough results 1) Bed 1 drain blocking filter 2) Relocate access panels bed 1 & 3 3) VIP suite filter slot (Victor) 4) Bed 2 damper blocking filter racks — Victor to change all ceiling AHU filter racks.
19.0 🔴 CRITICAL Bed 3 service wing framing — failed inspection, correction needed Omar Open ASAP Inspections sheet Framing inspection passed except staff/service wing. Correct and recall.
20.0 🔴 CRITICAL P&P Plumbing — demand letter still required Greg/Chana Open ASAP Omar control board Pattern documented. Demand letter required per Omar's board. No resolution shown in Gregg's tracker.
21.0 🟠 HIGH Carousel mock-up — 5/7 at 2pm (Victor bending metal bar) Greg/Victor/Paul Scheduled 5/7/2026 OAC2 Brass inlay edge detail + deflection assessment with black tile. Paul (Argent) reviewing. Written confirmation of pricing + credit needed.
22.0 🟠 HIGH 2nd floor soffit alignment issues — site walk 5/7 Omar/Greg Scheduled 5/7/2026 OAC2 Owner videos flagged misalignments. Resolve during site walk. Document corrective actions.
23.0 🟠 HIGH Borges on site 5/7 to discuss facade metals with Omar Andres/Omar Scheduled 5/7/2026 OAC2 Brake metal: Andres sent marked-up shop drawings 5/6 evening. Victor to site measure + samples. Alex color approval needed.
24.0 🟠 HIGH Landscape — Matthew on site 5/7, 2 signed/sealed copies for city Greg Scheduled 5/7/2026 OAC2 Matthew bringing plans for city processing.
25.0 🟠 HIGH Metal fencing — hidden areas to pickets, decorative at visible, add screens Greg/Victor Open 5/13/2026 OAC2 Marked drawings needed: decorative vs picket by location. Also add privacy screens for garage electrical panels + exterior water heaters + Jandy panels.
26.0 🟠 HIGH Civil engineer Marco — Omar sketch to reduce fees Omar/Greg In Progress 5/13/2026 OAC2 Gregg spoke to Marco. Omar sending sketch to reduce scope/fees.
27.0 🟠 HIGH Safe room doors — written quote, pick certified installer Chana Open ASAP OAC1 + OAC2 Will come back with quotes per OAC2. Must pick installer before safe room door supplier can make shop drawings.
28.0 🟠 HIGH Royal Laser — phased delivery discussion, Alex watching Chana Open ASAP Task List Alex asking for delivery target date. Chana to contact Greg Orsini (Royal Laser) about phased delivery.
29.0 🟠 HIGH Tub filler + drain — her master bath, core drill + rough Omar/Plumber Open ASAP Task List Omar to core drill. Plumber installs rough in floor.
30.0 🟠 HIGH Anti-scalding valve — her master bath (inspector requires) Chana/Plumber Open ASAP Task List Chana sending detail. Plumber will find spot after rough is in floor.
31.0 🟠 HIGH Freon lines master mech closet — lower (told Gabriel at 5/6 walk) Gabriel/Omar Open ASAP Task List Told Gabriel at walkthrough. Follow up to confirm.
32.0 🟠 HIGH Seal access panel back of elevator shaft Omar Open ASAP Task List Omar ordering panel that seals/locks. Confirm lock with Chana before ordering.
33.0 🟠 HIGH German (ELD) — 1st floor walk scheduled 5/20 Greg/Omar Scheduled 5/20/2026 Task List After German completes 2nd floor. Omar meets German for 1st floor schedule.
34.0 🟠 HIGH Gabriel — 1st floor HVAC walk scheduled 5/20 Greg/Omar Scheduled 5/20/2026 Task List Coordinate with 1st floor electrical walk.
35.0 🟠 HIGH Stair ceiling mirror — rosette detail, drawings from Arquitek in Procore Andres/Greg Open 5/13/2026 OAC2 Wood rosette to conceal chandelier lift. Millworker wood frame + separate mirror vendor. Latest drawings from Arquitek in Procore.
36.0 🟠 HIGH NWF — gym floor proposal owed Chana Open ASAP Task List NWF owes gym floor proposal. Chana to follow up.
37.0 🟠 HIGH File front door — PVT to provide NOA Chana Open ASAP Task List NOA needed for permit.
38.0 🟠 HIGH File garage door — NOA from John Buck, then complete inspection Chana Open ASAP Task List Get NOA then finish inspection.
39.0 🟠 HIGH Shearwall — pedestals shop drawing for exterior wood deck Chana/Greg In Progress ASAP Task List Comments sent 5/1. Shop drawing needed for pedestals.
40.0 📅 SCHEDULE New schedule — after 2F drywall + stone coordination Greg/Omar/Chana Open After drywall progress OAC2 5/6 Greg/Omar/Chana to build new schedule after completing 2F drywall and coordinating flooring install on 2F.
41.0 📅 SCHEDULE Next OAC — 5/13/2026 at 12:00 PM or 12:30 PM All Scheduled 5/13/2026 OAC2 Proposed time change from 1:30pm to noon or 12:30.
NEW 🟠 HIGH Camera payment — BRLH to pay, not CEM Greg Open ASAP Omar control board / Michael Omar's board notes 'Michael → cameras.' CORRECTION: cameras are BRLH's expense. Gregg to confirm with BRLH office/accounting. Michael has no payment obligation here.
NEW 🟠 HIGH Pool equipment payment — through Cinthia at BRLH accounting Gregg / Cinthia Open ASAP Michael update 5/6 Pool contractor approved. All equipment payments to be processed through Cinthia (BRLH accounting). Not a CEM action item.
NEW 🟠 HIGH Epoxy coating samples — acquire and have on site for owner review Greg Open 5/13/2026 OAC 5/6 + Michael update Engage Premier or specialist. Obtain epoxy floor coating samples for garage. Owner must review samples on site before decision. Coordinate with Argent walkthrough on garage cabinetry.
NEW 🟠 HIGH Jib doors for AC mech closets — Gregg to review Lujo product + pricing Greg Open 5/13/2026 Michael update 5/6 Two jib doors: one inside chef's kitchen AC mech closet, one just outside. These are BASIC (non-custom) doors now in the drywall scope — NOT Royal Laser millwork. Chana priced from Lujo. Gregg to review Lujo product and pricing.
NEW 🟠 HIGH AV Room HVAC — clarify exact equipment needed Greg Open 5/13/2026 Michael update 5/6 Gregg to determine exact equipment spec for AV room HVAC. Not a CEM item. Include in Gregg's tracker.
NEW 🟠 HIGH Royal Laser installer — Gregg + Omar + Alex to decide on site Gregg / Omar / Alex Open Next joint site visit Michael update 5/6 Gregg and Omar to discuss with Alex directly next time all three are on site. Decision: Russians as installer vs. BRLH sourcing another. Must be agreed in person — not via email or OAC.
NEW 🟠 HIGH Garage cabinetry decision — cover in Argent walkthrough Argent / Chana / Greg Open Next Argent visit OAC 5/6 + Michael update Determine in Argent walkthrough whether any garage cabinetry design is needed. Separately: Premier epoxy samples must be on site for owner review. Both items to be addressed together.
NEW 📋 INFO AGG Glass Contractors — gym glass wall shop drawings in progress Michael (CEM) / AGG Glass In Progress Post-drywall inspection Michael update 5/6 AGG Glass Contractors (Owner's contractor) handling gym glass wall. Initial shop drawings underway. Final measurements require finished wall, ceiling, and floor. Then fabrication. BRLH to ensure room completion is sequenced accordingly.
NEW 📋 INFO Shower enclosures / ribbed glass / mirrors — Katia + Chana + Greg Gregg / Chana Open TBD Michael update 5/6 CEM has no role. Assign to Gregg and Chana. RFPs sent to All Comp, Studio Glass, Champion Welding. BRLH to manage selection process.
5/13 ✅ RESOLVED Interior priming — APPROVED to start week of May 18 Gregg / Chana ✅ APPROVED 5/13 5/18/2026 OAC3 5/13 Decision made at OAC3. Painter to mobilize week of May 18.
5/13 ✅ RESOLVED Propane tank anti-flotation drawings — David Rogers completed Andres ✅ DRAWINGS COMPLETE 5/13/2026 OAC3 5/13 Stamped drawings ready. Now needs to be processed with city.
5/13 ✅ RESOLVED Main house transformer reorientation — REJECTED ✅ CLOSED 5/13/2026 OAC3 5/13 Too costly + FPL 8-foot clearance required. Orientation stays as-is.
5/13 🔴 CRITICAL Cryotherapy chamber — 230V vs 208V conflict, transformer noise, heat load Gregg / Tony Open — Researching Alt. 5/20/2026 OAC3 5/13 Cryofast unit requires 230V, house provides 208V. Noisy transformer required. 2-5kW heat load. Research 208V American units and split-unit options. Send Alex specs.
5/13 🔴 CRITICAL Deck & fire pit substructure — Manuel engineered drawings URGENT Manuel Open — Crew Waiting ASAP OAC3 5/13 Pedestals have no NOA. New plan: PT wood substructure by Manuel. Drawings are priority — crew will stop without them.
5/13 🔴 CRITICAL Drywall screw inspection — pass by end of week 5/11 Omar In Progress 5/14/2026 OAC3 5/13 Plumbers on site May 14 to complete so ceilings can close.
5/13 🔴 CRITICAL Facade/brake metal — color decision needed to proceed Andres / Victor Open — Color TBD 5/20/2026 OAC3 5/13 Victor's engineer reviewing fastening details. Color must be decided before shop drawings can be finalized.
5/13 🟠 HIGH City handrails — front steps + fire pit steps (new requirement) Andres Open 5/20/2026 OAC3 5/13 City courtesy walk resulted in minor handrail additions required. Andres to incorporate into fencing revision.
5/13 🟠 HIGH Roof fencing VE — white/less expensive alternative Andres / Victor In Progress 5/20/2026 OAC3 5/13 Ronaldo opposed black fencing on white roof. Alex concerned about appearance. Explore less expensive white solution. Andres to get VE marked-up drawings from Victor.
5/13 🟠 HIGH Landscape tree locations — conflict with underground utilities Gregg / Matthew Open 5/20/2026 OAC3 5/13 Trees on landscape plan conflict with underground utilities. Site walk needed with landscape architect.
5/13 🟠 HIGH SDS tile installer on site May 14 + Daniel starts May 15 Omar / Gregg Scheduled 5/14–5/15 OAC3 5/13 Exterior stone installer kickoff also May 15. Pool contractor job walk May 15.
5/13 🟠 HIGH Carousel — negotiate price + SDS installation method meeting May 14 Gregg / Chana In Progress 5/14/2026 OAC3 5/13 Brass inlays expected May 14. Meet SDS to approve installation method.
5/13 🟠 HIGH Noisy transformer — find insulated location, get specs from German Gregg / German Open 5/20/2026 OAC3 5/13 Possible cryo unit transformer described as 'jet engine' loud. Must find new location.
5/13 🟠 HIGH Argent — master carpet selection + bathroom 2 digital slab layout Paul / Argent Open 5/20/2026 OAC3 5/13 Paul to push Argent. Alex to be involved in carpet selection.
5/13 🟠 HIGH Electrician proposal for step-up transformer — get and review with Alex Gregg Open 5/20/2026 OAC3 5/13 Obtain electrician's proposal for transformer. Share with Alex for decision.
5/13 📅 SCHEDULE Next OAC — May 20, 2026 at 12:00 PM All Scheduled 5/20/2026 OAC3 5/13 Week of May 25 to be scheduled earlier for Alex.
5/18 ✅ RESOLVED Drywall screw inspection — 2ND FLOOR PASSED 5/18/2026 Omar / Lujo Drywall ✅ PASSED 5/18 5/18/2026 Daily Log 5/18 CRITICAL MILESTONE. Entire 2nd floor passed. Lujo adding 10 finishers 5/19. 1F drywall starts 5/19. Backing installation begins 1F.
5/18 🔴 CRITICAL P&P Plumbing — ABSENT 6 CONSECUTIVE DAYS (5/11–5/18). Demand letter NOW. Gregg / Chana Open — Demand Letter Required IMMEDIATE Manpower Log 5/18 Zero presence 5/11 through 5/18. Lujo starts 1F tomorrow. Condensate drains and tub/shower roughs must be done before ceilings close or they get drywalled in permanently.
5/18 🔴 CRITICAL SE Florida Mechanical — absent 5/13–5/18. HVAC punch items must clear before 1F ceiling closure. Gregg / Gabriel Open — Escalate IMMEDIATE Manpower Log 5/18 6 consecutive absences. HVAC punch list from 5/6 walk still open. Must clear before 1F ceilings close — bed 1 drain, access panels, VIP filter slot, bed 2 damper racks.
5/27 🔴 CRITICAL Veneer approval — TIME CRITICAL before June 15 Royal Laser 2F Paul / Alex / Argent Open — URGENT BEFORE 6/15 OAC5 Must approve: her closet, his & her vanities, massage vanity, cabana bar. June 15 is hard deadline.
5/27 🔴 CRITICAL Gas Rough Inspection — TODAY 5/27. Pass = call 1F Framing Omar / Andres Inspection Today 5/27/2026 OAC5 If gas passes today, call 1F framing inspection immediately.
5/27 🔴 CRITICAL Back deck structural / shearwall (Manuel) — contested Gregg / Manuel / BRLH Open — Contested This week OAC5 Omar says drawings show option; BRLH claims extra cost. Manuel coming this week.
5/27 🔴 CRITICAL FPL Easement — retrieve, notarize, submit Miami-Dade Michael (CEM) Open ASAP OAC5 Covenant at 188 marina (Marty). Must retrieve → notarize → submit to county before FPL relocates transformers.
5/27 🟠 HIGH Interior louvers — bottom detail unresolved Borges / Victor Open — site visit needed ASAP OAC5 Victor needs Borges comments. Borges wants site visit to finalize.
5/27 🟠 HIGH Gym glass wall header — scope active Gregg / AGG Glass In Progress TBD OAC5 AGG Glass (Owner's contractor) shop drawings in progress.
5/27 🟠 HIGH Luhho jib door specs — millwork sequencing Gregg In Progress TBD OAC5 Part of millwork sequencing. Gregg to confirm specs.
5/27 ✅ RESOLVED Sheet piles — wall gap closure APPROVED Gregg / Omar ✅ APPROVED 5/27 Done OAC5 Chana sent 5/26. Alex approved at OAC5.
5/27 ✅ RESOLVED Culligan water filtration — DECIDED Chana ✅ DECIDED 5/27 Done OAC5 Alex: RO to main kitchen faucet + $999 UV button upgrade.
5/27 ✅ RESOLVED Propane tank — delivered Chana ✅ RESOLVED Done OAC5 Delivery this week, no storage charge.
5/27 📅 SCHEDULE Next OAC — June 3, 2026 at 11:00 AM All Scheduled 6/3/2026 OAC5 Confirmed.

OAC #5 — MAY 27, 2026 (Most Recent)

Attendees: Chana Sweetbaum, Omar Rodriguez, Gregg Covine, Michael Pingree (CEM), Craig Morton (BRLH), Andres Ramirez (Borges), Alex Shnaider, Reinaldo Borges

# Topic Status / Decision Action Item Owner Due Flag
1.0 Safety — Platform leg at top of stairs RESOLVED — temporary for plywood subfloor, replaced. No action. Omar Done DONE
2.0 Site cleanliness / Windows Craig noted exterior spots being addressed. Windows must be closed EOD. Enforce daily. Omar Daily INFO
3.0 Civil revision — Marco Osorio Still pending full civil revision. Marco issued grading plan without 'not for construction' note. Follow up with Marco. Andres / Marco 6/3 ACTION
4.0 Facade horizontal metal specs Chana sent to Andres today for review. Andres to confirm. Andres 6/3 ACTION
5.0 Wellness — Cryotherapy conduits Proceeding with Stefano directing conduit placement. Gregg calls Stefano back to site to mark exact locations. Gregg / Stefano ASAP CRITICAL
6.0 Landscape — Matthew / LAND Sunshine 811 scheduled to mark seawall area this week. Site walk with Matthew/Omar after. Confirm 811 markings then schedule walk. Gregg / Omar This week ACTION
7.0 Roof HVAC isolators — permit submission Signed permit app received back. Will now submit to city. Submit to city immediately. Chana ASAP ACTION
8.0 Fencing / railings VE Michael issued instructions on sections. Final proposal from Victor pending. Obtain final proposal from Victor. Chana / Victor 6/3 CRITICAL
9.0 Interior louvers — bottom detail Victor needs Borges comments on shop drawings. Borges wants site visit. Schedule Borges site visit to finalize. Borges / Victor ASAP ACTION
10.0 Shearwall — back deck / fire pit Manuel coming this week. Monitor. Push for delivery. Gregg / Manuel This week ACTION
11.0 Shearwall — column under wellness room Drawings received today. Sent to Borges & BNI for approval. Await Borges / BNI. Borges / BNI ASAP ACTION
12.0 Cabana bath door — shop drawings + NOA Pending. Michael P to send to team. Michael to provide. Michael (CEM) ASAP ACTION
13.0 Aquadynamics — pool heater / window conflict Pool equipment delivered yesterday. Mario coming for layout. Schedule Mario for equipment layout. Mario / Gregg ASAP ACTION
14.0 Veneer — owner approval ⚠ TIME CRITICAL STILL PENDING: her closet / his & her vanities / massage vanity / cabana bar. Paul coordinating once new samples arrive. Must approve BEFORE June 15 Royal Laser 2F delivery. Paul / Alex / Argent BEFORE 6/15 CRITICAL
15.0 Safe room doors — 2 installations Liliana requested COI from installer. Follow up on COI. Route to ownership once confirmed. Chana ASAP ACTION
16.0 Culligan water filtration — DECIDED DECIDED by Alex: RO attached to main kitchen faucet + $999 UV button upgrade. Proceed per direction. Chana Done DONE
17.0 Driveway proposals Still leveling. Will send to ownership for approval. Complete leveling. Route to ownership. Chana / Gregg 6/3 ACTION
18.0 Sheet piles — wall gap closure — APPROVED APPROVED. Chana sent proposal 5/26. Alex approved at OAC5. Proceed with installation. Gregg / Omar ASAP DONE
19.0 Slabs from Detroit Katia inspecting tomorrow (5/28). Katia to inspect and report. Katia 5/28 ACTION
20.0 Sill risers Omar ordering from Atlantic. Confirm delivery date. Omar ASAP ACTION
21.0 Propane tank delivery — RESOLVED Delivery this week, no storage charge. No action. Chana Done DONE
22.0 Tape & finish — 2nd floor In progress. Monitor. Omar / Harold Ongoing INFO
23.0 Royal Laser — schedule revision ⚠ Greg Orsini on site. Revised: 2F FIRST. June 15 — 2nd floor vanities. Confirm veneer approval before June 15 delivery. Gregg / Greg Orsini 6/15 CRITICAL
24.0 El Gant — exterior stone starts June 15 Confirmed. Confirm start. El Gant / Omar 6/15 ACTION
25.0 SDS — waterproofing On site. Monitor. SDS / Omar Ongoing INFO
26.0 Daniel Tile — kickoff Came today. Coming Monday for layout then waterproofing. Confirm Monday appointment. Daniel / Omar 6/1 ACTION
27.0 Swimming pool — float slab Need to float slab under equipment. Delta owes proposal. Chase Delta Construction. Chana / Delta ASAP ACTION
28.0 1F pre-drywall mechanical walk Omar has Gabriel's list and is working items. Complete items before walk. Omar / Gabriel TBD ACTION
29.0 1F pre-drywall low voltage walk Walk done with Benny. Working on list. Complete items. Omar / Benny TBD ACTION
30.0 Gas rough inspection — TODAY 5/27 Inspection TODAY. Pass → call 1F framing inspection. Confirm pass/fail. Call framing if gas passes. Omar / Andres 5/27 CRITICAL
31.0 Electrical — 1F rough ~2–3 more weeks for German to complete 1F rough. Monitor. German / Omar ~6/17 ACTION
32.0 City storm drain cleaning Mike Garcia out until 6/1. Follow up 6/1. Omar 6/1 ACTION
33.0 Mosquito misting trims Coming next Wednesday for test fit. Confirm. Omar 6/3 ACTION
34.0 Exterior speakers + light trims Coming from Maxicon / trims ordered. Confirm arrival and install schedule. Gregg / Maxicon TBD ACTION
35.0 FPL easement — recording Covenant signed. Need to record. Michael: retrieve from Marty @ 188 marina → notarize → submit Miami-Dade. Michael (CEM) ASAP CRITICAL
36.0 Next OAC meeting June 3, 2026 at 11:00 AM. Confirm attendees. All 6/3 SCHEDULE

OAC #4 — MAY 20, 2026

Attendees: Chana, Omar, Gregg, Michael (CEM), Craig Morton, Andres, Vlad, Tony, Alex | Next OAC: 5/27 at 11:00 AM

# Topic Status / Decision Action Item Owner Due Flag
1.0 Safety — Elevator 2F Opening Omar added fall protection at elevator opening 2F. Resolved. No further action. Omar Done DONE
2.0 Site Cleanliness / Windows Drywall dust daily — Omar enforcing sweep up. Windows MUST be closed at end of every day — rainy season. Enforce daily at closing. Omar Daily INFO
3.0 MEP Revision — City APPROVED APPROVED. Chana picked up from city 5/20. Resubmitted 5/18, approved same week. File approved plans. Proceed with gas tank and related work. Chana Done DONE
4.0 Propane Tank Slab — Rogers Inspection Rogers needs to inspect slab once steel is in place. Rogers to inspect when steel ready. Gregg / Rogers Post-steel ACTION
5.0 Civil Revision — Marco Osorio Still pending full civil revision. Marco provided grading above propane tank. Andres reissuing grading plan without Not For Construction label. Follow up with Marco for target date. Andres / Marco 5/27 ACTION
6.0 Facade Metal — Color Decision Color to match window frames. Victor providing. Shop drawings needed from Victor for Borges review. Andres reaching out to Victor for shop drawings. Andres / Victor 5/27 CRITICAL
7.0 Wellness Center — Cryotherapy DECIDED DECIDED: Alex purchasing unit himself. Stefano installs after final inspections. Transformer in electrical room. Split condenser on roof low wall outside wellness room. Gregg calls Stefano back to site to give Omar exact conduit needs and locations. Gregg / Omar ASAP DONE
8.0 Landscape — Matthew (surgery) Matthew had surgery. Will contact Gregg when ready to walk. Call Sunshine 811 to locate underground infrastructure between pool deck and seawall before tree walk. Gregg Post-recovery ACTION
9.0 Roof HVAC Isolators — Ownership Signature BNI stamped. Permit app sent to ownership (Trust/Texas) for signature 5/18. STILL WAITING. Ownership to sign immediately. Chana to follow up. Owner / Chana ASAP CRITICAL
10.0 Fencing & Railings VE Borges met Victor 5/19. Preparing summary for Alex on design changes and pricing. New city handrails needed at front and back stairs. Borges presented to Alex at OAC4. Still pushing to finalize VE. Finalize VE with Borges. Victor to produce shop drawings. Process with city. Borges / Victor 5/27 CRITICAL
11.0 Interior Louvers Victor needs Borges comments on shop drawings submitted. Borges to review and comment. Then coming to site to discuss. Borges / Victor ASAP ACTION
12.0 Shearwall — Pool Deck & Fire Pit Working on engineering drawings. Pushing Manuel every few days. Critical to keep Bozzui working. If Manuel slow — call BNI. Keep pushing Manuel. Alert BNI if no delivery by 5/27. Gregg / Manuel ASAP CRITICAL
13.0 Shearwall — Column Under Wellness Manuel addressing Borges comments. Monitor. Manuel 5/27 ACTION
14.0 Cabana Bath Door — Shop Dwgs + NOA Shop drawings and NOA needed. Obtain shop drawings and NOA. Chana / Gregg ASAP ACTION
15.0 Argent — Master Carpet Selection Argent to work with owner to select. Paul to push Argent. Alex to decide. Paul / Argent 5/27 ACTION
16.0 Carousel Upcharge — REJECTED REJECTED by Alex. Does not approve $3,200 + $750 upcharge. Alex may revisit later. Drop current proposal. Close item for now. Gregg / Chana Closed DONE
17.0 Safe Room Doors Confirm installer insurance before sending to ownership. Chana to verify insurance then route to ownership. Chana ASAP ACTION
18.0 Culligan Water Filtration Met on site 5/19. Proposal being sent to ownership. Route Culligan proposal to Michael for owner approval. Chana ASAP ACTION
19.0 Driveway Proposals Leveling in progress. Will send to ownership. Complete leveling. Route to ownership. Chana / Gregg 5/27 ACTION
20.0 Royal Laser — Vanity Veneer Alex and Greg Orsini meeting 5/20 for veneer approval. Shipping vanities second week of June. One week transit. Vanity install 2F late June. Confirm Alex approves veneer today. Track June shipping. Pending veneer approval. Alex / Greg Orsini 5/20 CRITICAL
21.0 Exterior Wood Ceilings — Extra Wood RESOLVED: Bozzui confirmed 5/20 — no additional wood planks needed to finish ceilings. No action. Omar Done DONE
22.0 Slabs from Detroit Katia going to inspect. Will email results. Katia to inspect and report. Katia ASAP ACTION
23.0 Sheet Piles — Wall Gap On site. Installation pending Sunshine 811 locating underground. Call Sunshine 811. Proceed once cleared. Gregg / Omar ASAP ACTION
24.0 Brass Floor Inlay Bars Received on site. SDS to make carousel edge mock-up. SDS to make mock-up with brass bars. SDS / Omar ASAP ACTION
25.0 Basemold Riglet On site. Blocked by sill riser installation. Chasing Infinite Windows. Chase Infinite Windows for sill risers. Gregg / Chana ASAP ACTION
26.0 Propane Tank Delivery Dumpster relocated. Requesting delivery this week. Confirm delivery date. Chana This week CRITICAL
27.0 Drywall Inspection — PASSED PASSED. Tape and finish in progress. Priming pushed back one week — dust + inspection timing. Harold to start priming when ready — week of 5/25. Harold / Chana Week of 5/25 DONE
28.0 El Gant Kickoff — Exterior Stone El Gant kickoff meeting today 5/20. Commencing exterior stone installation. El Gant starting. El Gant / Omar 5/20 DONE
29.0 SDS — Waterproofing + Carousel Sergio starts waterproofing 5/21-22. Approved crack suppression plan. Warranty company to inspect. Thinks he has enough black slabs — to confirm. SDS starts 5/21. Confirm black slab quantity. SDS / Omar 5/21 ACTION
30.0 Daniel Tile — 2 Bathrooms 2 bathrooms only. Pending Daniel measuring. Schedule Daniel to measure. Chana / Daniel ASAP ACTION
31.0 Swimming Pool — Float Slab Equipment arriving ~2 weeks. Need to float slab under equipment — sloped. Chana getting price from Delta Construction for slab float. Chana / Delta ASAP ACTION
32.0 Royal Laser — Vanity Shipping Shipping second week of June. One week transit. Install 2F late June. Pending veneer approval 5/20. Track shipping. Confirm veneer approval. Gregg / Greg Orsini June CRITICAL
33.0 1F Pre-Drywall Mechanical Walk 5/21 at 10am — Gabriel AND Craig MUST attend. Gregg to confirm Gabriel and Craig attendance. Gabriel / Craig / Gregg 5/21/2026 CRITICAL
34.0 1F Pre-Drywall Low Voltage Walk 5/21 at 12pm — Benny AND Craig MUST attend. Gregg to confirm Benny and Craig attendance. Benny / Craig / Gregg 5/21/2026 CRITICAL
35.0 Pending Change Orders 'Chana?' noted on agenda — no CO list provided at OAC4. Chana to provide CO list before or at 5/27 OAC. Chana 5/27 ACTION
36.0 New Master Schedule Gregg/Omar/Chana to build after 2F drywall and flooring coordination. Build schedule after 2F drywall complete and flooring sequenced. Gregg / Omar / Chana After 2F drywall ACTION
ADDITIONAL DETAIL FROM MEETING TRANSCRIPT — CROSS-REFERENCED 5/20/2026
A1 Civil — Slab Elevation Confirmation Needed Civil plan shows 'preliminary / not for construction' — shell contractor hesitant to proceed. Need written confirmation that bubbled area slab elevations (e.g. 7 NGBD) will not change. Andres to get written confirmation OR have Marco reissue bubbled sheet without preliminary stamp for propane tank/generator area only. Andres: written elevation confirmation OR reissue bubbled sheet without preliminary stamp for propane/generator area. Andres / Marco 5/22/2026 CRITICAL
A2 Generator Screening + Fencing — Owner Package Due 5/25 Generator ~69 inches tall — must be elevated above flood level. City requires permanent screening (landscaping supplements only). Owner: white fences, minimalist, clean V-shape resort look. Rooftop: vertical tubes (lower cost) vs vertical fins (better concealment) — need apples-to-apples pricing. Pool fence minimum 48 inches. Cable rail vs vertical picket at pool equipment path — white finish preferred. Marina-to-pool deck gates required by city. Equipment stacking may exceed screen height — panels designed to be removable for service. Prepare user-friendly drawing + pricing summary for Alex by 5/25. Include fence/screen options with clearances. Review Andres drawing with city to confirm 3-foot clearances for generator + condensing unit. Bracket-mounted unit behind fence preferred — no new slab. Gregg / Andres / Victor 5/25/2026 CRITICAL
A3 Pool Equipment Layout — Field Meeting with Aquadynamics (~2 weeks) Focused field meeting needed with Mario (Aquadynamics) to resolve pool equipment layout, gas water heater/window clearances, egress, and fence height within code. River rock preferred over slab for maintenance. Schedule field meeting with Aquadynamics within ~2 weeks to finalize equipment layout and fence strategy. Gregg / Mario (Aquadynamics) ~6/3/2026 ACTION
A4 Wine Condenser Location — City Clearances Wine condenser placement needs code clearances. Consider consulting mechanical inspector. Alternative location feasible with fence extension — owner prefers no new slab. Maxicon panel may be movable — verify code. Consult city mechanical inspector on wine condenser clearances. Verify Maxicon panel movability. No new slab if possible. Gregg / Andres 5/27/2026 ACTION
A5 Wellness Center — Cryotherapy Conduit Rough-In Detail Stefano's direction: rough-in conduits NOW (exterior conduit for condenser + conduit to electrical room for possible transformer) before final inspections. Install cryotherapy unit AFTER final inspections/occupancy to avoid MEP revisions. Prefer 208V outdoor split system. Avoid water-cooled units requiring chiller. UL listing not required for private residence post-occupancy — confirm with AHJ/insurance if non-UL unit considered. Gregg to call Stefano back to site to mark exact conduit locations for Omar. Rough-in conduits before walls close. Gregg / Stefano / Omar ASAP CRITICAL
A6 Culligan Water Treatment — DECIDED Culligan recommends: whole-house filtration + RO at kitchen only. NO dedicated RO or softener for steam shower — RO output ~1.8 gpm insufficient for ~2.0 gpm demand, plus space constraints. Owner agreed: proceed without RO/softener for steam. Domestic water split ground floor + 2F with constant-pressure booster pumps. Commission at farthest fixtures (master high-flow shower) with balancing valves. Send updated Culligan proposal to Alex and Michael for approval. Commission domestic water system at farthest points. Document pump control logic. Chana / Michael (CEM) ASAP DECISION
A7 Facade Break Metal — Prior Scope Incorrect, Drawings Poor Prior shop drawings from Victor had incorrect scope and poor drawing quality. Marked-up drawings were emailed. Victor must re-review based on markups — not just the original submission. Resend marked-up drawings to Victor. Victor to re-review and resubmit corrected shop drawings. Andres / Victor 5/27/2026 CRITICAL
A8 Interior Louvers — Stone Connection Detail + On-Site Review Framing reportedly complete. Louver-to-stone connections needed — pin connection under stone. Argent provides design intent. On-site meeting needed to align details and expedite approvals. Schedule on-site meeting to finalize louver details. Provide timely approvals/comments to Victor. Andres / Victor / Argent ASAP ACTION
A9 Shearwall Manuel — ULTIMATUM: Firm Timeline by EOD or Replace Owner instruction at OAC4: if Manuel does not provide firm timeline TODAY (5/20), engage alternate engineer known to Omar. Ronaldo (Borges) to submit to city. BNI is the backup. PT wood substructure is the approach — must be engineered for hurricane/impact zone. City disallows plastic pedestals without NOI. Manuel: firm timeline by EOD 5/20 or REPLACE with alternate engineer. If replaced: Omar's contact + BNI. Rinaldo to submit to city. Gregg / Borges / Manuel EOD 5/20/2026 CRITICAL
A10 Irrigation — Start Meter Process + Shop Drawings Start irrigation meter process now due to lead times. Irrigation subcontractor to produce shop drawings per Matthew's plans. Matthew to review/approve after recovery. Utility locating and exploratory excavation near seawall before Matthew's site walk. Start irrigation meter process. Irrigation sub produces shop drawings. Utility locating before any excavation near sheet pile. Gregg / Chana ASAP ACTION
A11 Bozzui — Finish Ceilings This Week Then PAUSE Russian crew (Bozzui) to finish exterior wood ceilings this week. Then PAUSE — no next scope until vanities arrive AND deck/fire pit plans AND millwork are ready. Do not start new scope without all three in place. Omar to confirm ceiling completion. Communicate pause instruction to Bozzui. Omar This week ACTION
A12 Master Carpet Selection — LOW PRIORITY Arjun (Argent) to confirm with owner. Low priority — not holding anything up. Arjun to confirm with Alex. No urgency. Argent / Arjun Low priority INFO
A13 Roof HVAC Isolators — Ownership Signature via FedEx BNI stamped drawings complete. Permit app sent to ownership (Trust/Texas). Expected to arrive via FedEx for signature. Ownership to sign and return FedEx immediately upon receipt. Owner / Chana Upon receipt CRITICAL

OAC #3 — MAY 13, 2026

Attendees: Gregg Covine, Omar, Andres, Alex, Victor, Manuel, Tony, Paul + others | Next OAC: May 20, 2026 at 12:00 PM

# Topic Decision / Outcome Action Item Owner Due Date Status
1.0 Site Safety & Cleanliness Sinkhole by garage repaired with concrete. Hard hats now enforced for Bart Reines employees. Site cleaned after drywall. Tracks vacuumed before insulation/drywall install. Strictly enforce window closure at end of each day — rainy season started. Protect new drywall. Omar Daily Ongoing
2.0 Propane Tank Anti-Flotation Device David Rogers completed drawings. Hard copies of MEP revision provided by Andres. Process stamped anti-flotation device drawings with the city. Andres / Chana ASAP Open
3.0 Civil Revision — Marco Osorio Marco received site plan and city comments. Civil revision in progress. Follow up with Marco on civil revision progress next week. Gregg 5/20/2026 In Progress
4.0 Facade / Brake Metal — Color Decision Needed Meeting held with Borges on facade metal. Victor's engineer reviewing markups on brake metal shop drawings to add fastening details. Color must be decided before work can proceed. Work with Victor on facade metal color. Andres to get final marked-up shop drawings from Victor with VE changes. Andres / Victor / Gregg 5/20/2026 Open — Color TBD
5.0 Landscape Plan — Tree Relocation Landscape architect's plans show trees conflicting with underground utilities. Schedule walk-through with landscape architect to relocate conflicting trees. Gregg / Matthew 5/20/2026 Open
6.0 City Courtesy Walk-Through Results City approved sheet piles for seawall gap. Minor handrail additions required on front steps and fire pit steps. Andres to incorporate new handrail requirements into fencing revision. Andres 5/20/2026 Open
7.0 Fencing & Railing VE — Roof Fencing Design Major VE discussion. City handrail requirements being incorporated. Ronaldo opposed VE for roof fencing — original plan was high-end louver system to hide tall condensing units. Alex: black fencing on white roof looks ugly. DECISION: explore less expensive, possibly white, fencing solution for roof and generator areas. Andres to get final marked-up shop drawings from Victor reflecting VE changes (pickets vs decorative, roof fencing solution). Andres / Victor 5/20/2026 In Progress
8.0 Wellness Center — Cryotherapy Chamber (CRITICAL ISSUE) Selected Cryofast machine (French) requires 230V. House provides 208V — noisy step-up transformer required. Unit generates 2–5 kW heat. Condenser system 6 at max. System 2 could handle at 120% capacity (needs owner approval). Three-phase electrical cannot be changed. Research American-made 208V cryotherapy units and split-unit options (external condenser/chiller) to avoid transformer + AC mods. Send Alex picture + specs of proposed cassette unit. Gregg / Speaker 3 5/20/2026 Open — Researching Alt.
9.0 Wellness Center — AC Solution Engineer Tony proposed 1.5-ton supplemental cassette unit. Linear less-obtrusive cassette preferred for aesthetics. Investigate less obtrusive AC cassettes. Determine which rooms are served by condenser system 2. Gregg / Tony 5/20/2026 Open
10.0 Transformer Noise Issue Separate transformer (possibly cryo unit) identified as extremely noisy ('jet engine'). Must find new insulated location. Get technical specs for noisy transformer from German. Find suitable insulated location. Gregg / German 5/20/2026 Open
11.0 Main House Transformer Reorientation ✅ REJECTED — too costly, must maintain 8-foot FPL clearance. Orientation stays as-is. No action — closed. Closed ✅ Closed
12.0 Carousel Turntable — Pricing & Installation Proposal received. Price negotiation underway. Simple gear modification proposed to slow it down. Brass floor inlays expected May 14. Call carousel supplier to negotiate lower price. Meet with SDS tile installer May 14 to approve turntable installation method. Gregg / Chana 5/14/2026 In Progress
13.0 Deck & Fire Pit Substructure — NOA Issue Originally planned pedestals have no NOA and are unapproved. New plan: pressure-treated wood substructure designed by Manuel. Drawings are priority to prevent work stoppage. Manuel to provide engineered drawings for PT wood deck and fire pit substructure. PRIORITY — crew waiting. Manuel ASAP Open — URGENT
14.0 Interior Painting — Priming Approved ✅ DECISION: Interior priming approved to start week of May 18. Coordinate painter mobilization for week of May 18. Gregg / Chana 5/18/2026 ✅ Approved
15.0 2nd Floor Drywall Screw Inspection Goal: pass drywall screw inspection by end of week of May 11. Plumbers scheduled May 14 to complete work so ceilings can be closed. Plumbers on site May 14. Close ceilings after plumbing complete. Omar / Plumber 5/14/2026 In Progress
16.0 Tiling — SDS & Daniel SDS (main installer) on site May 14. Second installer Daniel starts May 15. Exterior stone installer kickoff May 15. Coordinate SDS May 14 start and Daniel May 15 start. Stone installer kickoff May 15. Omar / Gregg 5/14–5/15/2026 Scheduled
17.0 Argent Input — Bathroom Digital Slab Layout + Master Carpet Argent's input needed for bathroom 2 digital slab layout and master carpet selection. Paul to push Argent for master carpet selection with Alex. Paul / Argent 5/20/2026 Open
18.0 Gym Glass Wall — Shop Drawings Shop drawings awaiting final ceiling layout and drywall inspection completion. AGG Glass to proceed with shop drawings once ceiling layout final and drywall inspection passed. Michael (CEM) / AGG Glass Post-drywall inspection Open
19.0 Safe Room Doors — Written Quote Sean provided verbal quote of $1,500/piece. Written quote still pending. Get written quote from Sean for both safe room doors. Chana ASAP Open
20.0 Shower Glass — Height Clarification Argent needs to clarify heights. Believed only steam room glass goes to ceiling. Speaker 10 (Shana?) to receive all shower information from Shana for framing. Argent to clarify. Argent / Chana 5/20/2026 Open
21.0 Roof HVAC Isolators — Matthew Follow-Up Follow-up needed with Matthew regarding isolators. Gregg to follow up with Matthew on roof HVAC isolators. Gregg 5/20/2026 Open
22.0 Material Status Update Riglets on site. Sheet piles on site. Slabs from Detroit in transit. Brass floor inlays expected May 14. Confirm brass floor inlay delivery May 14. Track Detroit slab delivery. Gregg / Omar 5/14/2026 In Transit
23.0 Next OAC — May 20, 2026 at 12:00 PM Confirmed. All parties to attend. Week of May 25 OAC to be scheduled earlier for Alex. All 5/20/2026 Scheduled

OAC #2 — MAY 6, 2026

OAC #1 — MAY 1, 2026

Complete Active / scheduled In progress Planned Critical hold Today
Phase / TaskOwnerStatus 4/14 4/21 4/28 5/5 5/12 5/19 5/26 6/2 6/9 6/16 6/23 6/30 7/7 7/14 7/21 7/28 8/4 8/11 8/18 8/25 9/1 9/8 9/15 9/22 9/29 10/6 10/13 10/20 10/27 11/3 11/10 11/17 11/24 12/1 12/8 12/15 12/22 12/29 1/5 1/12 1/19 1/26 2/2 2/9 2/16 2/23
LIFE SAFETY & CRITICAL HOLDS
⚠ Gas Revision — walls CANNOT close Chana ⚠ Trouble
⚠ HVAC Supply Duct Failure — demand letter Gabriel Chana ⚠ Trouble
Gas WH — Underground Elec. Conflict (CO~3wk) Chana ⚠ Trouble
Front Facade — Stone vs. Paint DECISION Chana ⚠ Trouble
ENVELOPE & EXTERIOR
Elevator — Rails + Permit ✅ Omar ✅ Done
Remove Scaffolding Omar ✅ Done
Stucco (Dennis SC) — started 4/21 Chana In Progress
Foam Panel Fabrication ✅ Chana ✅ Done
Foam Panel Ext. Install Chana Scheduled
Riglets T&G — powder coating (Wed) Omar Open
LED Metal Strip — galvanize (DUE 4/29) Omar Open
Aluminum Cladding Omar Open
Wood Ceilings Omar Open
Ext. Patio Stone Chana Open
Stone Terraces Omar Open
Glass Railings Omar Open
Spiral Stair & Railings (release scope) Greg Open
Retaining Wall — Public Works Chana Open
Pavers / Driveways Greg Open
Roof Metal Equipment Enclosure Greg Open
MEP ROUGHS
Rough Wiring & Distribution ✅ Omar ✅ Done
Low Voltage ✅ Omar ✅ Done
Plumbing Rough (Power Plumbing — started 4/20) Omar In Progress
⚠ Condensing line insulation scope — Horiz. TBD Chana ⚠ Trouble
⚠ Wine Wall & AV HVAC Rough Omar ⚠ Trouble
HWH / DOB Approvals Chana Pending
Gas Piping (pend. inspection) Omar In Progress
ELD Electrical — started 4/28 ✅ Omar In Progress
ELD Metal — started 4/27 ✅ Omar In Progress
Garage A/C Relocation Greg Open
Transformer / Pedestals (Marina) Chana Open
CIVIL & SITE
French Drain Relocation (Thurs 4/30) Greg Scheduled
Pile Schedule + Inspection Omar Open
Slab — Start + Rebar + Completion Omar Open
Back Fill Omar Open
Propane Tank — Survey + Delivery Chana Open
Gas Tank Coordination Chana Open
Pipe Work (City — clean, no lining) Chana Open
POOL & EXTERIOR AMENITIES
Pool Equipment Release + Start Greg Open
Pool Pedestals + Deck Shop Dwgs Greg Open
Fire Pit Shop Drawings Greg Open
Garage Doors — release for production Greg Open
DRYWALL & SHELL CLOSE
Lujo Drywall — Master His/Her ✅ (ceilings + walls) Omar ✅ Done
Drywall Finish (7 days) Omar In Progress
Framing Inspection Omar Open
Drywall — All Areas Omar Open
Plaster / Compound / Cornerbeads Omar Open
MILLWORK & FINISH TRADES
Millwork Production (underway) Chana In Progress
SDS Stone — Material→Layout→Cut→Install Chana Open
Stone Backing + Vanity L-Angles (dates TBD 🔴) Chana Open
Royal Laser (June Glamm — June 2026) Omar Open
Floor Heating — Material Ordered 4/21 ✅ Chana ✅ Done
Millwork Install Omar Open
Closets Omar Open
Doors & Casing Omar Open
Counters Omar Open
Appliances Chana Open
FLOORING
Stone Flooring & Bathrooms Omar Open
Wood Flooring Delivery + Install Omar Open
Flush Baseboard (Tri-County) Omar Open
ELECTRICAL & MEP FINISHES
HVAC — Master Wing (owner approval) Chana Open
Steam Room Lighting (owner confirm) Chana Open
Electrical Trim / Keypads / Fans Greg Open
Mechanical Finishes Greg Open
MAXICON — shade wire/alarms/speaker Omar Open
CONTRACTS & APPROVALS
Interior Painting — revise + resend proposal Chana Open
Exterior Painting — new proposal (25% darker) Chana Open
Paint Selections — OWNER APPROVALS NEEDED 🔴 Chana ⚠ Trouble
Electrical Fixtures — Maxicon confirm scope Omar Open
INTERIOR FINISHES
Final Painting Chana Open
Specialty Wall Finishes Greg Open
Shower Glass & Mirrors Greg Open
Door Hardware + Window Treatments Greg Open
Stair Finishes / Rail Greg Open
Carpet Greg Open
CLOSEOUT
Rolling Punchlist (start Dec 2026) Greg Open
TCO Application Chana Open
Testing & Balancing / Commissioning Greg Open
Cleaning / De-mob / Close Out Greg Open
🎯 TARGET COMPLETION — FEB 28, 2027 BRLH 🎯 TARGET
In Progress Scheduled Planned

ROUGH INSPECTIONS

Low Voltage✅ Passed · Maxicon
Windows Buck - Anchoring✅ Passed · Infinite
Roof In Progress✅ Passed · Bustos
Mechanical Rough✅ Passed · SE Mechanical
Fire Alarm Rough✅ Passed · Delta Tech
Framing Rough✅ Passed (except Staff/Service Wing) · Passed except Staff Area / Service Wing · BRLH
Insulation✅ Passed — 4/14/2026 · Icynene at roof slab · JAJ
Drywall Screw — 2nd Floor✅ PASSED — 5/18/2026 · CRITICAL MILESTONE. Entire 2nd floor passed. · Lujo Drywall
Plumbing Rough (shower pans & insulation)✅ Passed — 4/16/2026 · Gym & Master Shower Pans / Pipe insulation · P&P Plumbing
Gas Rough🔴 TODAY — 5/27/2026 · Scheduled today. Pass → call 1F Framing inspection. · P&P Plumbing
Electrical Rough⏳ Partials · Pending Ground Floor & Garage (~2–3 more weeks) · Delta Tech / German
1F Framing Inspection⏳ PENDING GAS PASS · Will call immediately if gas rough passes today (5/27). · BRLH

UPCOMING INSPECTIONS

Wall InsulationUpcoming
Drywall Screw — 1st FloorUpcoming — after 1F rough complete
Roof FinalUpcoming
Plumbing FinalUpcoming
Electrical FinalUpcoming
Mechanical FinalUpcoming

SCOPES MISSING TO CLOSE

Guest Bath 3Smart Glass — unknown if being done
Guest Bath 3Blocking at ceiling (in case client wants later)
Guest Bath 3Window removal/reinstall — pending decision
Guest Bath 3Pipe Insulation
Guest Bath 3Wall Insulation
Guest Bed 3Blocking for Roller Shades

▶ SHOP DRAWINGS | Submittal Log

Glass Railing

Brake Metal

Main Stair Guard Rails

Wine

Millwork

Planters

Low Voltage

Louvers

Garage Door

Pedestals

# Item Submitted To By Alex Decision Date Notes / Next Step
1.0 Plumbing — 2nd Floor Balancing Valves ($1,200) Michael Chana ✅ APPROVED 5/4/2026 Verbal price approved.
2.0 Electrical — Prado Outlets ($3,900 — Delta Tech) Michael Chana ✅ APPROVED 5/4/2026 Approved by Alex 5/4.
3.0 Electrical — Floor Boxes ($4,213 — Delta Tech) Michael Chana ⚠ PARTIAL 5/4/2026 Approved EXCEPT wellness room. Reprice pending.
4.0 HVAC — Master Wing — no additional AC units Alex Greg/Chana ✅ NO AC — CLOSED 5/4/2026 Decided by Alex 5/4.
5.0 Shades — motorized massage room only Chana/Maxicon Greg ✅ DECIDED 5/6/2026 Massage: motorized. Staff/baths: manual.
6.0 Foyer foam panels — run to floor, seal all sides Omar/Jennifer Argent ✅ DECIDED 5/6/2026 Argent confirmed. Instructions issued.
7.0 Stair Guard Rail CO Michael Chana ✅ APPROVED Prior Per Chana's tracker.
8.0 Smart Glass Film Michael Chana ❌ REJECTED Prior Rejected per Chana's tracker.
9.0 Baseboard Milling & Install Michael Chana ✅ APPROVED Prior Per Chana's tracker.
10.0 Wine Unit — Ductless Slimline Michael Chana ✅ APPROVED Prior Per Chana's tracker.
11.0 Metal Fencing & Enclosures ($530,809) Alex/Michael Chana ⏳ VE IN PROGRESS OAC5: Michael issued instructions on sections. Final proposal from Victor pending.
12.0 Interior Painting — Harold Alex Greg/Chana ✅ PRIMING APPROVED 5/13/2026 Interior priming approved OAC3. Painter mobilized.
13.0 Carousel — speed reduction gear upcharge Alex Chana ✅ UPCHARGE REJECTED 5/20/2026 Alex rejected $3,200 + $750 upcharge at OAC4.
14.0 Civil Engineer Marco — additional fees Alex Greg ⏳ PENDING Omar sketch in progress to reduce scope.
15.0 Water Filtration — Culligan Alex/Michael Chana ✅ DECIDED — OAC5 5/27/2026 RO to main kitchen faucet + $999 UV button upgrade. Alex directed 5/27.
16.0 Wellness Center — Cryotherapy unit Alex Greg/Andres ✅ DECIDED 5/20/2026 Alex purchasing unit himself. Stefano directing conduit rough-in.
17.0 Gym Glass Wall (AGG Glass) Michael (CEM) / AGG Glass BRLH ⏳ SHOP DRAWINGS IN PROGRESS AGG Glass (Owner's contractor). Shop drawings in progress.
18.0 Safe Room Doors (~$1,500/door) Michael Chana ⏳ COI PENDING ASAP Liliana requested COI. Must verify insurance before routing to ownership.
19.0 Jib Doors — AC Mech Closets Greg Chana ⏳ GREG TO REVIEW Two door types. Greg reviewing.
20.0 AV Room HVAC Greg Chana ⏳ GREG TO CLARIFY Greg to determine exact equipment spec.
21.0 Millwork Installer for Royal Laser Gregg / Omar / Alex Chana ⏳ ON-SITE DISCUSSION Gregg and Omar to discuss with Alex directly.
22.0 Landscape Plans (Matthew / LAND) Alex Greg ⏳ PENDING Post-recovery Matthew had surgery. Sunshine 811 scheduled for marking then site walk.
23.0 Garage Cabinetry & Slat Walls (Premier) Argent / Chana Chana ⏳ ARGENT WALKTHROUGH Decide during Argent walkthrough.
24.0 Shower Enclosures, Ribbed Glass & Mirrors Gregg / Chana Chana ⏳ PENDING CEM no role. Gregg and Chana manage.
25.0 Fire Feature — Galio Planika Fire Bowl Alex BRLH ⏳ PENDING Purchase fire bowl. Fill slab below.
26.0 Dock Demo Alex Chana ⏳ PENDING Pending proposal from Shore.
27.0 Sheet Piles — Wall Gap Closure Alex / Chana Chana ✅ APPROVED — OAC5 5/27/2026 Chana sent proposal 5/26. Alex approved at OAC5. Proceed immediately.
28.0 Veneer — Her closet / His & Her vanities / Massage / Cabana bar Alex / Paul (Argent) Argent ⏳ PENDING ⚠ TIME CRITICAL BEFORE 6/15 Must approve before June 15 Royal Laser 2F delivery. Paul coordinating.
Bid Package/Description of Work Sub Contractor Buyout Status/Comments Awarded
Final Cleaning Proposals to be retrieved
Utility Easement There will be a cost to this scope for the Marina. Proposal previously submitted to be updated with new scope
Retaining Walls Borges designing new scope. In AOR Court
Grading side & rear yards Onsite Removal of material/grading
Site Fencing Champion Welding Borges reviewing scope/Chana making scope document so Alex can get other proposal
Poured Concrete Driveway & Walkways RFPs sent to two subs
Landscaping, Irrigaton, Landscape Lighting Pending landscape design
Brake Metal Champion Welding Review to capture all areas, verify color at front façade
Baseboard Tri County Proposal from Tri County provided, $13plf. Need to identify linear foot necessary and revise proposal
Millwork - Built-Ins, Vanities, Interior Doors, & Closets Royal Laser/Arquitek Pending two jib doors at mech closet in chefs kitchen/mech closet. Pending wood ceiling at kitchen island
Interior Painting Oleg or Harold Pending interior paint proposal. Oleg's received.
Repricing water Feature & Stone surround at door L-Gant Tile Pending proposal
Gym Flooring (Material & Install - Wood Plank & Wood Border) NWF Requesting additional planks for gym 2.
Wood Decking at Pool Deck Russians ? Chana tracking down proposals for wood deck from Russian
Fire Feature Purchase of Galio Planika fire bowl - fill in slab below
Garage Cabinetry & Slat Walls Premier Design Needed from ownership, Premier Garage proposal needed
Shower Enclosures & Doors, Ribbed Glass, & Mirrors RFP's sent out on Friday. Sent to All Comp, Studio Glass, Champion Welding
Plumbing Fixtures & Accessories Ferguson Complete flush plate purchase, garbage disposal push button, outdoor kitchen sink & faucet
Whole House Water Filter Circulate Proposals & leveling to ownership
Water Bug One Proposal received from Oasis. Wireless. Maxicon providing alternate

🚧

ACTIVE WORK (ON SITE NOW)

(What should be happening / being pushed daily)

HVAC

Diffusers delivered → installation needs to be actively underway

Ceiling coordination tied directly to HVAC progress

Pushing manpower from Gabriel ⚠️

Electrical

Rough + ongoing electrical work progressing

Panel + routing coordination ongoing

Preparing for continued inspections

Framing / Interior Coordination

Framing dependent on:

Louver details from Borges

Ceiling coordination (HVAC + lighting)

General Progress

Easy installation phase remaining (per your note)

Site should be in execution mode, not planning mode

BLOCKERS / ISSUES (STOPPING PROGRESS)

🚨 HVAC Manpower

Gabriel not providing enough workers

Diffusers on site but install not moving fast enough

→ Action: Letter escalation already required

🚨 Power Plumbing

Repeated no-shows

→ Demand letter required

→ Direct impact on inspections + progress

🚨 Gas Line (CRITICAL PATH)

TECO change not finalized:

3” low → 2” high pressure

→ Must be resolved before downstream work

🚨 Louver Details (Borges)

Missing install details

→ Blocking framing progress

PENDING (NEEDS ACTION / FOLLOW-UP)

Proposals / Financial

Painters proposal

Interior flooring proposal

Exterior flooring proposal + layouts + submittals

Approvals

Owner approvals (create structured tracking)

Electrical revisions (Aaron)

Gas system approval

Exterior finishes selections

Site / Utility

Mailbox location confirmation

Irrigation meter

Overflow pipe cleaning scheduling

Coordination

Transformer + panel location approval (Tony)

Responsibility

Michael → payment for cameras

🔮

UPCOMING WORK (NEXT PHASES)

Flooring & Finishes

Finalize pavers (exterior)

Execute flooring installations

Painting scope execution

Exterior Scope

Finalize fencing → move to production

Determine boat dock removal + permits

Landscaping

Final landscaping plans

Resolve mango tree decision

Feature Elements

Glass railing execution

Water feature redesign (black granite / black stone)

🚨

CRITICAL PATH (TOP 6 DRIVERS)

(These control your schedule — everything else is secondary)

Gas line conversion (TECO)

HVAC manpower + diffuser install + ceilings

Power Plumbing reliability

Louver details → framing release

Electrical approvals (keep inspections moving)

Pending approvals (owner + subs)

🧠

SITE EXECUTION REALITY (IMPORTANT)

Right now your job is in a danger zone phase:

You have materials on site ✅

You have partial inspections passed ✅

But manpower + coordination gaps are slowing execution ⚠️

👉 This is where projects either:

Accelerate hard, or

Get stuck for weeks

🎯

WHAT YOU SHOULD BE PUSHING DAILY

If you strip everything down, your daily focus should be:

Force HVAC manpower onsite

Lock gas decision immediately

Push plumbing accountability

Get Borges to release louver details

Keep electrical moving toward inspections

Eliminate any waiting on decisions

▶ GREG'S MASTER TASK UPDATES | Rev 5/18/2026

GREEN = Done/Resolved | RED = Critical/Blocker | ORANGE = In Progress | PURPLE = New intel
#Category · Item · Gregg's Status (5/18) · Owner
1.0Exterior / Site · LED Metal Strip — galvanize · DONE · Omar
2.0Civil · French Drain Relocation · DONE · Omar
3.0Exterior · Foam Panel Finish — No painting · DONE — Decided no painting · Omar/Chana
4.0Civil / Structure · Piles — done and installed · DONE — Rogers will inspect slab steel · Omar
5.0Exterior · Riglets — received full delivery, being installed · DONE — Delivery received, installation underway · Omar
6.0Exterior / Site · NWF gym floor proposal · DONE and APPROVED · Chana
7.0Permits · Garage door — NOA received · In progress — NOA got it, Chana/Gregg preparing app · Chana / Gregg
8.0Exterior · Spiral Stair & Railings — Victor fabricating · Victor starting fabrication 5/15 · Victor / Campion
9.0Exterior / Civil · Transformer / Marina — easement complete · Easement complete and recording in process after owner signature · Chana / Owner
10.0Permits · Condenser vibration isolators — ownership signature needed · Shops done by David Rogers / BNI stamped. Chana sent to Trust (Texas) 5/18 for signature. · Owner / Chana
11.0Permits · MEP Revision — resubmitted 5/18 · Chana/Gregg resubmitted to address comments 5/18 · Chana / Gregg
12.0Permits · Building Inspector Valente — front door slab/steps · Borges meeting with building official to try to get approval. Engineer letter needed. · Borges / Gregg
13.0Wellness / HVAC · Cryotherapy — new 208V unit + split condenser on roof (Alex's supplier meeting 5/18 3pm) · Meeting with new cryo supplier from Alex 5/18 at 3pm. 208V power and split condenser hidden on roof. · Gregg / Alex
14.0Propane · Propane tank delivery — take delivery or storage charges begin · Chana emailed asking to wait till mid-May, no reply. Will call — waiting to relocate dumpster. · Chana / Gregg
15.0Permits · Window permit close-out — reprint stickers + sheetrock · After drywall — will need to reprint stickers and be sheet rocked · Gregg / Omar
16.0Permits · Shearwall — re-engineering in wood (no pedestals, no NOA) · Manuel re-engineering in wood. Follow up 5/20. · Manuel / Gregg
17.0Framing · Chef kitchen AC — Michael P does not want elevator shaft supplied by chef kitchen AC · Discuss with Gabriel at 5/6 walkthrough and get proposal · Gabriel / Gregg
18.02F — Finishes · SDS Sergio — started measuring 5/15, 2F waterproofing/floor heating pads after drywall screw inspection · Sergio started measuring 5/15. Will commence 2F waterproofing + floor heating mud-in after drywall screw inspection. · SDS / Omar
19.02F — Finishes · Daniel tile — coming week of 5/18 to measure · Coming week of 5/18 to measure · Daniel
20.02F — Finishes · Harold — start priming after drywall screw inspection (week of 5/18) · Harold to start priming after drywall screw inspection 5/18 · Harold / Chana
21.0Exterior / Facade · Gas WH Electrical Conflict (Herman CO) — APPROVED, need electric work done · Approved — need electric work done · Herman / Gregg
22.0Pool · Pool equipment — met Mario 5/15, equipment coming in ~2 weeks · Met with Mario 5/15. Equipment arriving in approximately 2 weeks. · Mario / Gregg
23.0Exterior · Carousel — final price $3,200 parts + $750 install · Gregg called again. Final reduction: $3,200 parts / $750 install. Total $3,950. · Gregg / Chana
24.0Exterior · Garage Doors — cladding sequence discussion with PVT · Discussed cladding install sequence with PVT/John. Waiting for John to call back. · Gregg / John (PVT)
25.0Exterior / Civil · Driveways — leveling sheet being created · Chana creating leveling sheet for 2 proposals. Need to confirm if included in city revision. · Chana / Gregg
26.0Site / Civil · Pipe Work (City) — Mike Garcia visited 5/15 · Mike Garcia (city) visited site 5/15. Owed proposal. Follow up 5/20. · Gregg
27.0Exterior · Fire Pit — PT wood structure. Proposal from Russians (Bozzui) once Shearwall issues drawing · PT wood structure decided. Get proposal from Bozzui once Shearwall drawing issued. · Gregg / Bozzui
28.0Permits · Gas Tank — after delivery, approved revision needed to proceed · After delivery, need approved revision to proceed. Andres working the revision. · Andres / Chana
29.0Electrical — 1F · German 1F electrical — says 3 weeks to complete · German says 3 weeks for 1F electrical completion. · German / Gregg
30.0Finishes · Wine display — sample wood needed before July delivery commit · Royal sending wood sample to approve then send to Tanner. Cannot commit to early July delivery without sample approval. · Chana / Gregg
31.0Finishes · Royal Laser — closed 5/18 holiday, discussing schedule 5/19 · Closed 5/18. Will discuss schedule with Greg Orsini on 5/19. · Gregg / Greg Orsini
32.0Finishes · Shower glass — Chana sent latest RFP to Gregg · Go through all with Omar. Chana sent Gregg latest RFP. · Gregg / Omar / Chana
33.0Permits · Isolator shops — done, need Trust signature · Done by David Rogers/BNI stamped. Need signed by ownership — Chana sent to Texas (Trust) to sign. · Owner / Chana
34.02F — Electrical · Top of elevator shaft — German needs detail. Light fixture? · German needs detail. Who buys fixture — German or BRLH? · German / Gregg
35.02F — Electrical · Wellness room — 208V power + split condenser (from Alex cryo meeting) · Meeting 5/18 3pm with Alex's cryo supplier. 208V unit + split condenser hidden on roof. · Gregg / Alex / Tony
36.02F — Electrical · Remodel cans — wellness entry / VIP bedroom closet · Need spec from Maxicon sent to German. Chana to approve and order. · Chana / Maxicon / German
37.02F — Electrical · VPS ceiling cans for steam room (2 needed) · Omar has materials and location. Will install. · Omar
38.02F — Mechanical · Seal access panel back of elevator shaft · Omar does not like current access panel. Chana to order replacement. · Chana / Omar
39.02F — Mechanical · Water test all HVAC condensate drains in ceiling · Omar to make plumber do it after drywall. Plumber should test all condensate drains. · Omar / Plumber
40.01F — Mechanical · Transfer in laundry room — needs framing in hallway · Gabriel needs hallway framing. Chana to check dimensions/markings then Omar make framer do it. · Chana / Omar / Framer
41.01F — Mechanical · Framing for Gabriel office vestibule ceiling supply · 1F. Omar to make framer do it. · Omar / Framer
42.01F — Mechanical · China closet framing for supply box · 1F. Omar to make framer do it. · Omar / Framer
43.01F — Mechanical · Curved diffuser — Gabriel to deliver, coming 5/19 · They are on site. Gabriel coming 5/19. · Gabriel / Omar
44.0Exterior / Stone · Brass bar inlay sample — Sergio needs to make carousel mockup · Brass bars coming. Ask Chana — Sergio needs for carousel mockup. · Chana / Sergio
45.0Exterior / Stone · Carousel mockup — SDS checking for black slabs. Crack suppressant plan agreed. · SDS agrees with Omar's plan. Will add crack suppressant under tile. Company to inspect and own warranty. · SDS / Omar
46.0Finishes · Stucco punch list — Gregg/Omar to walk and clean up · Gregg/Omar walk stucco punch list and clean up. · Gregg / Omar
47.0Finishes · Sill riser — waiting on higher gauge material from Lazaro · Infinite Windows waiting on Lazaro to receive higher gauge material. · Lazaro / Estevan
48.0Finishes · El Gant — waiting for scaffold and wood to be moved for kickoff · El Gant coming for kickoff. Waiting for scaffold and wood to be moved. · Omar / Gregg
49.0Finishes · Sconce spec near turntable — coordinate with German · Coordinate sconce spec near turntable wall with German. · German / Gregg
50.0Landscaping · Matthew — surgery last week. Call after 5/20 for tree walk · Matthew had surgery. Contact after 5/20 to schedule tree walk with Omar re underground conflicts. · Gregg
51.0Permits · Stucco — Gregg/Omar to walk punch list · Gregg/Omar walk stucco punch list and stucco clean up. · Gregg / Omar

▶ GREG'S TASK LIST | Rev 5/18/2026

ItemAction · Responsibility note · Action

Second floor (PRIORITY WORK)

Electric-German

Top of elevator shaftGerman needs detail · German owes light fixture? Or we buy?
Plan for additional equipment in Wellness roomMeeting with new Cryo supplier from Alex 5/18 @3pm · 208 power and split condenser hidden on roof
Remodel cans in access panel Wellness entry/VIP Bdrm closetNeed Spec from Maxicon sent to German · Need to approve spec · Chana approve and order
Need 2 VPS ceiling cans for steam roomOmar has materials and location will install
Final location chandelier up/down control switchConfirm with German · Inside AV closet
Steam Room LightingFinalize steam room lighting design. Confirm with ownership. MAXICON to set speaker in steam room ceiling (separate but coordinated). · Pending 2 speakers and 1 chromosome light

Mechanical-Gabriel

Seal access panel back of elevator shaftOmar does not like the access panel we have · Chan will order
water tast all in ceiling hvac condensate drainsOmar make plumber/ · Omar after drywall plumber should do it
Bedroom 2 damper blocking filter victor needs to change filter racks all ceiling AHU'sVictor changing filter racks

Plumbing- Power Juan Pablo

Tub fillerHer master · Need jp to install
Tub drainHer master · Need jp to install
Anti scaldingHer master · Need jp to install
Balancing valvesCeiling outside master door · Need jp to install
Rain shower roughsNeed jp to install

LV Maxicon Benny

steam room2 speakers and chromosome light

Bedroom 3 flip the keypad and thermostat

Finishes

Stone SDSSergio started measuring 5/15 and will commence second floor waterproofing/floor heating pads mud in/after drywall screw inspection second floor
Daniel tileComing week of 5/18 to measure
delta electricianPrado Outlets proposal · Done waiting on electrician to provide and install
Royal LaserGreg orsini · Closed for holiday on 5/18 will discuss schedule on 5/19
Master His & HerPaint Sub · Paint — Harold start priming after drywall screw inspection 5/18
Master His & HerMaxicon (unconfirmed) · Argent provides Id fixtures
NWFOwed us gym floor proposal · Done and approved
Shower glassGo thru all with Omar · Chana sent Gregg latest RFP
Wine displayNeeds sample wood before he can commit to early July delivery · Royal sending us wood sample to approve then send to Tanner

First Floor

Electric-German

Electrical — First Floor CompletionProvide completion date. Includes revised lighting plan + all relocations. ELD starting date 4/28. Blocks drywall close on first floor. · German says 3 weeks
Carousel USAProposal to Alex — to install metal gear · Gregg called again - Final reduction they offered is $3200 parts/ $750 install
Sconce spec for wall near turntableCoordinate with German

Mechanical-Gabriel

Gabriel first floor walk thruScheduled for 5/20
Transfer in laundry room 1 floorGabriel says he needs framing hallway · Chana check dimensions and markings then Omar make framer do it
Framing for Gabriel office vestibule ceiling for supplyFirst floor · Omar make framer do it
China closet framing in ceiling for supply box1 floor · Omar make framer do it
Michael P doesn't want the chef kitchen ac supplying the elev shaftDiscuss with Gabriel at 5/6 walkthru and get proposal$
Garage A/C RelocationUpdate plans for garage A/C relocation. Coordinate with mechanical drawings. · Discuss with Gabriel at 5/6 walkthru and get proposal$
Curved diffuserNeed from Gabriel · They are onsite Gabriel coming 5/19

Stone Systems MOCK UPS

Mock up brass bar inlay ? Need sample of brass barBrass bars coming? Ask Chana as Sergio needs to make carosal mockup
Mockup the carouselSDS checking if he has black slabs for this · SDS agrees with Omar's plan and will add crack suppressant under tile and have crack suppressant company come inspect to own the warranty

Exterior/Facade/Sitework

Take delivery of propane tank or they will start charging us for storageChana emailed and asked to wait to mid May no reply · Will call them waiting to relocate dumpster
Fire pit redoGoing to be PT wood structure · Get a proposal from Russians once Shearwall issues drawing
Gas Water Heaters — Electrical ConflictRelocate underground electrical lines conflicting with gas line location. Proposal/CO pending from Herman (~3 weeks). Requires owner approval to proceed. Status needed immediately. · approved need electric work done
Pool Equipment ReleaseRelease pool equipment to subcontractor to start. Pool pedestals, pool deck shop drawings, fire pit shop drawings all pending. · Met with Mario on 5/15 equipment coming in approx 2 weeks
Transformer / Pedestals (Marina)Finalize pedestals and relocation plan. Coordinate with marina/utility provider. · Easement complete and recording in process after owner signature
Garage Doors ReleaseRelease garage doors for production. No further design holds — ready to issue. · Need to discuss cladding install sequence with PVT/John garage door guy - explained to Doug at garage door co & waiting for John to call back
Spiral Stair & RailingsRelease scope. Begin coordination. Proceed to installation. Coordinate with metal fabricator (Campion Welding / Victor Tuckler). · Victor starting to fabricate 5/15
LED Metal Strip for stepsGalvanize. Approved on site. DEADLINE: 04/29/2026. Coordinate with Campion Welding. · Done
Riglets — T&GPowder coating by Wednesday. Feeds exterior wood ceiling and baseboard reglet installation. · Received full delivery being installed
Pool AreaPool pedestals. Pool deck shop drawings. Fire pit shop drawings. Coordinate with pool equipment release. · Waiting on Shearwall to re engineer no pedestals
Retaining Wall (Public Works)Finalize solution for retaining wall with Public Works. Coordinate with civil. · Sheet piles approved by city/chana will send proposal to Michael for approval
Roof — Metal Equipment EnclosureShop drawings → fabrication → installation sequence. Coordinate with metal fabricator and roofing. · Included in Champion Welding fencing quote under review. Not a separate CEM approval — part of overall fencing scope decision.
French Drain civil RelocationScheduled for Thursday. Check required — confirm contractor mobilized and work proceeding. · Done
Gas Tank CoordinationCoordinate gas tank installation with propane delivery, survey, and civil work. · After delivery need approved revision to proceed / Andres is working the revision
Pipe Work (City)Clean pipe — no lining. Coordinate with city. Likely related to French drain / civil scope. · Mike Garcia visited site 5/15 owed proposal follow up 5/20
Foam Panel SubFluted foam panels — stone vs. painted DECISION NEEDED · Decided no painting · Installation completion target · 5/31/2026
DrivewaysDecide between 2 proposals · Chana creating leveling sheet · Need to see if included in current revision being processed at city
Pile Contractor propane tankInspection + 10-day mobilization lead · Piles done and installed · Rogers will inspect when he inspects slab steel
StuccoDennis Service Corp · Gregg/Omar walk stucco punch list and stucco clean up
Infinite Windows — EstevanSill riser issue · Waiting on Lazaro to receive higher gage material
El Gant coming for kickoffWaiting for scaffold and wood to be moved
LandscapingMatthew has surgery last week call after 5/20 to schedule tree walk with Omar re: underground conflicts
Water meter /gas meterGregg will follow up

Roof

Condenser vibration isolatorsengineering prepping design for stands · Shops received from David Rogers/stamped by BNI · Waiting for ownership to sign permit app Chana sent to Trust on 5/18

Permitting

******Building inspector Carlos Valente needs to see evidence of inspecting front door new slab and steps that got pouredMet with inspector need to recall inspection of front stairs and at grade landing slab, have engineer letter when he comes · Borges meeting with Bld Official to try to get approval
MEP REVISONChana/Gregg already resubmitted to address comments on 5/18
File front doorPVT to provide NOA · Still pending NOA fromPVT
File garage doorIn progress · Chana/Gregg preparing app we got the NOA
Close out window permitWe will need to reprint stickers and be sheet rocked · After drywall
Shearwall is engineering pedestals for exterior wood deckNo pedestals no NOA · Manual re engineering in wood follow up 5/20
Isolators shopsDone by David Rogers/Stamped by BNI · Need signed by ownership Chana sent to Texas for the Trust to sign

▶ MASTER TASK LIST | Site Task Log

Second floor (PRIORITY WORK TO DRYWALL)

Electric-German

list from 4/28 walk thruGerman says done by 5/1
Master headboard sconcescall Garde re mounting detail · Gregg · X
Top of elevator shaftGerman needs detail · German owes light fixture
Plan for additional equipment in Wellness roomVlad sending comments also on this 5/6 · Andres will follow up with Tony and discuss next OAC2
Remodel cans in access panel Wellness entry/VIP Bdrm closetNeed Spec from Maxicon sent to German · Need to approve spec · Chana approve and order
Need 2 VPS ceiling cans for steam roomMight be on site · Gregg tell German/Omar will babysit layout · Omar make German install
Final location chandelier up/down control switchConfirm with German · Inside AV closet
German needs exterior sconce locations marked outside massage room balconyCheck plans and have Omar mark wall · Gregg · X done except low one on side of walkway
Steam Room LightingFinalize steam room lighting design. Confirm with ownership. MAXICON to set speaker in steam room ceiling (separate but coordinated). · X
Master bath floor heaterCheck out control trim and how does heater meet window/floor thickness? · Omar is going to examine it to confirm how it works against sill
Elevator smoke detectorMove to center line hallway in line with other smoke detector

Mechanical-Gabriel

HVAC — Supply Duct FailureSend demand letter to Gabriel. Supply ducts at plenums are coming apart. Immediate correction required. No response → escalate with Craig.-Gabreil says done by Friday 5/1 walk job with Gabreil on Wednesday 5/6 · Completed walk thru of second floor with Gabriel -Omar working on remaining open items on second floor
Pre drywall walk thruScheduled with Gabriel for wed 5/6 10am · Done 5 6
Freon lines in master mech closet need to be loweredNeed to tell Gabriel · Told Gabriel at walkthru
Insulate all horizontal condensate linesOmar make Gabriel do it/extra material arrives 4/30 · Omar/materials are here 5/1
remote ac sensors? in master and gymGabriel will do · We gave locations to Gabriel at walkthru
All fresh air dampers installed and working?Gabriel says yes 5/6 · Confirmed with Gabriel at walkthru
Seal access panel back of elevator shaftOmar does not like the access panel we have · Omar will order one that seals/lock or no lock?confirm lock with Chana before order
Return for mech closet in guest bed 1Try to get Tony M engineer to agree with return from corridor · Tony approved/ Omar says in progress and has all materials/ needs to draw from hallway Plenum also per Craig
water tast all in ceiling hvac condensate drainsOmar make plumber/ · Omar after drywall plumber should do it
make return from guest bed#1 to corridorTony PE approved and in progress/sent photos to Tony · Omar in progress
HVAC — Master WingFinal decision required. Requires owner approval before HVAC sub can proceed in master wing. Plenum in master hallway and gym also flagged 'Hot' on board. · Not adding additional unit for master
Bedroom 1 drain blocking filter - GabrielResults of 5/6 walkthru w/Gabriel
Relocate access panel bedroom 1 & bedroom 3- GabrielResults of 5/6 walkthru w/Gabriel
VIP suite needs slot for filter from victorResults of 5/6 walkthru w/Gabriel
Bedroom 2 damper blocking filter victor needs to change filter racks all ceiling AHU'sResults of 5/6 walkthru w/Gabriel

Plumbing- Power Juan Pablo

Tub fillerHer master · Omar will core drill and have have plumber install rough in floor
Tub drainHer master · Omar will core drill and have have plumber install rough in floor
Anti scaldingHer master · Plumber asking inspector Omar tell plumber we need one only has one valve/chana sending detail of device anti scald to Omar · Plumber says we need it and he will find a spot after the rough is in the floor
Balancing valvesCeiling outside master door · After core drill Plumber will locate a spot for it · ✅ APPROVED by Alex 5/4/2026 · Approved — written proposal to be resubmitted for file
Water supply line massage room to highOmar tell plumber

Rain shower roughs

LV Maxicon Benny

Did walk thru with Benny 4/29Benny says target is Friday 5/1
Chana / AV SubAV Change Order — confirm + process · Chana thinks no
MAXICONShade wire (dressing room) + alarm boxes + steam room speaker · Pre drywall check bennys work list
Does Benny instal steam room speakersOmar ask him

Bedroom 3 flip the keypad and thermostat

Finishes

His & Hers Bathroom Stone — Delivery ScheduleProvide date schedule for delivery to fabricator. SDS Stone process: Material → Digital Layout → Cut → Install. Backing date and vanity L-angles also TBD (flagged red on board). · BART wants list of which bathrooms/areas get stone first to start shop drawings · Chana make list of Second floor slab areas and email Bart/Gregg list
delta electricianPrado Outlets proposal · Done waiting on electrician to provide and install
Royal LaserGreg orsini · Alex asking for delivery target date · Chana contact Royal and discuss phased delivery
Master His & HerPaint Sub · Paint — master suites waiting for Oleg proposal
Master His & HerMaxicon (unconfirmed) · Argent provides Id fixtures
NWFOwed us gym floor proposal · Chana follow up

First Floor

Electric-German

Electrical — First Floor CompletionProvide completion date. Includes revised lighting plan + all relocations. ELD starting date 4/28. Blocks drywall close on first floor. · After German finishes 2nd floor Omar meets with German for first floor schedule and needs
Carousel USAProposal to Alex — to install metal gear · They reduced installation price but Alex wants us to push back and get credit for gear being removed

Mechanical-Gabriel

Gabriel first floor walk thruScheduled for 5/20
Transfer in laundry room 1 floorGabriel says he needs framing hallway · Chana check dimensions and markings then Omar make framer do it
Framing for Gabriel office vestibule ceiling for supplyFirst floor · Omar make framer do it
China closet framing in ceiling for supply box1 floor · Omar make framer do it
Michael P doesn't want the chef kitchen ac supplying the elev shaftDiscuss with Gabriel at 5/6 walkthru and get proposal$
Garage A/C RelocationUpdate plans for garage A/C relocation. Coordinate with mechanical drawings. · Discuss with Gabriel at 5/6 walkthru and get proposal$

Stone Systems MOCK UPS

Mock up brass bar inlay ? Need sample of brass barBrass bars coming 5/8
Mockup the carouselChana calling Opustone for some material Black Infinity Leathered

Exterior/Facade/Sitework

Take delivery of propane tank or they will start charging us for storageChana emailed and asked to wait to mid May no reply · Call by 5/15 and tell to deliver /Omar clear area and prep for delivery
Fire pit redoWood or concrete need to decide · Get a proposal from Russians for wood/delta owes a proposal
Gas Water Heaters — Electrical ConflictRelocate underground electrical lines conflicting with gas line location. Proposal/CO pending from Herman (~3 weeks). Requires owner approval to proceed. Status needed immediately. · approved need electric work done
Pool Equipment ReleaseRelease pool equipment to subcontractor to start. Pool pedestals, pool deck shop drawings, fire pit shop drawings all pending. · Invoice has been submitted to accounting, pending payment to commence work
Transformer / Pedestals (Marina)Finalize pedestals and relocation plan. Coordinate with marina/utility provider. · Surveyor preparing easement for recording by 5/6 folow up
Garage Doors ReleaseRelease garage doors for production. No further design holds — ready to issue. · Need to discuss cladding install sequence with PVT/John
Spiral Stair & RailingsRelease scope. Begin coordination. Proceed to installation. Coordinate with metal fabricator (Campion Welding / Victor Tuckler). · Victor should be starting to fabricate Omar confirm with Victor he started to fab
LED Metal Strip for stepsGalvanize. Approved on site. DEADLINE: 04/29/2026. Coordinate with Campion Welding. · Done
Riglets — T&GPowder coating by Wednesday. Feeds exterior wood ceiling and baseboard reglet installation. · Received partial deliver 5/1 · Infinitive is onsite cutting windows for ringlets 5/7
Pool AreaPool pedestals. Pool deck shop drawings. Fire pit shop drawings. Coordinate with pool equipment release. · Send the Craig markups to Shesrwall · Chana/Gregg
Retaining Wall (Public Works)Finalize solution for retaining wall with Public Works. Coordinate with civil. · Ball in Borges court to provide engineering detail
Roof — Metal Equipment EnclosureShop drawings → fabrication → installation sequence. Coordinate with metal fabricator and roofing. · Included in Champion Welding fencing quote under review. Not a separate CEM approval — part of overall fencing scope decision.
French Drain civil RelocationScheduled for Thursday. Check required — confirm contractor mobilized and work proceeding. · Done
Gas Tank CoordinationCoordinate gas tank installation with propane delivery, survey, and civil work. · After delivery need approved revision to proceed / Andres is working the revision
Pipe Work (City)Clean pipe — no lining. Coordinate with city. Likely related to French drain / civil scope. · Follow up with city pipe cleaning sub then Omar will camera it
Foam Panel SubFluted foam panels — stone vs. painted DECISION NEEDED · Decided no painting · Installation completion · 5/31/2026
DrivewaysGetting proposal
Pile Contractor propane tankInspection + 10-day mobilization lead · Scheduled for 5/11 pending approved revision that Andre's is working on
StuccoDennis Service Corp · Gregg/Omar walk stucco punch list and stucco clean up
Infinite Windows — EstevanSill riser issue · Conflict - RAUL saying he can provide new risers at no charge that snap on but Omar thinks you have to rip out sills to install and we need the new sills that snap on from infinite - need to sort this out asap
Omar list of details front entrance facadeOmar gave Gregg photo with list of details needed
Main house transformer can it oriente it E/W and make gate on the insideDiscussed with Alex - will try to hide with landscaping , doubt follow allows it to change

El Gant coming on 5/15 for kickoff

Roof

Condenser vibration isolatorsTrio engineering prepping design for stands · Follow up 5/6
Omar and Gregg walk roof make listWeek of 5/4

Permitting

******Building inspector Carlos Valente needs to see evidence of inspecting front door new slab and steps that got pouredMet with inspector need to recall inspection of front stairs and at grade landing slab, have engineer letter when he comes · Omar getting letter from S engineer BNI
Gas Revision (Life Safety)Finalize gas revision. Cannot close walls until completed. Required for final sign-off on life safety inspection. · Pending resvion from Andres
File front doorPVT to provide NOA
File garage doorGet NOA from John buck inspection then finish
Close out window permitWe will need to reprint stickers and be sheet rocked · After drywall
Shearwall is engineering pedestals for exterior wood deckSent comments to shearwall 5/1 · Need to process a shop drawing for the pedestals

▶ CHANA'S TRACKER

Construction Items In ProgressStatus/Date · Notes

Mechanical

Hood drop at Chefs KitchenUnderway · SE Mechanical
Hood Drop at main kitchenUnderway · SE Mechanical
Wine Unit RefrigerationUnderway · Pending approval to upcharge for slim line unit · SE Mechanical
AV Room CoolerUnderway · Reverting to dedicated AC unit · SE Mechanical
Pressurize system to indentify leaksUnderway · SE Mechanical
Garage Mini SplitsUnderway · Pending locations/drain/plywood blocking · SE Mechanical
Connect condensate drainsUnderway · SE Mechanical

Metals

Interior LouversPending · Shops/ Design update with Borges · Champion
Stucco & Knife Edge WorkUnderway · Champion
Bracket for Gym WindowUnderway · Champion
BRLH/ArgentLaying out FFE & Millwork · Underway
Blocking for TVsUnderway
Blocking for Roller ShadesUnderway

Framing

Framing for pocket doors at New GymUnderway · Lujo

Millwork

Vanity Support Locations - QuantityUnderway · Greg O to provide locations/BRLH to install · Royal Laser
Royal Laser Phase 1 Millwork Shops ApprovedSD's Approved · In Fabrication · Royal Laser
Royal Laser Phase 2 (Holding Laundry until plumbing complete)Underway · Royal Laser
Arquiteq Millwork Shop Drawings ApprovedSD's Approved · In fabrication · Arquitek

Electric

Complete Light Fixture Rough & Outlet RoughUnderway · Delta Tech
Complete Panel InstallationUnderway · Delta Tech

Low Voltage

Steam Speaker & Light RoughUnderway · Maxicon
Complete wiringUnderway · Maxicon

Finishes

Floor Floating/ LevelingUnderway · NWF
Exterior Tongue & Groove CeilingsUnderway · Bozzui
Paint Samples at ExteriorUnderway · Dennis

Plumbing

Plumbing -copper, shower pansUnderway · P&P Plumbing
Plumbing InsulationUnderway · P&P Plumbing
Her Master Bath Tub Filler Rough & Tub DrainUnderway · P&P Plumbing
Steam rough completion (aroma)Underway · P&P Plumbing

Propane Tank

Scaffold RemovalPending
Drive the (4) Helical PilesPending
Slab PourPending
Deliver/ Set/Pipe in TanksPending

Milestone Deliverables

Stone Deliveries05/01/2026
ID LightingTBD
MillworkTBD · Getting schedule from fabricators
Entry Pivot Door10/01/2026
Wood Flooring07/01/2026 · Expecting Arrival End of July
Wine Wall Display07/01/2026

Ownership Items - Change Orders to Review

Stair Guard RailPending · Pending ownership approval · Approved
Smart Glass FilmPending · Pending ownership approval · Rejected
Baseboard Milling & InstallPending · Pending ownership approval · Approved
Swing Doors for Chefs KitchenPending · Pending ownership approval
AV Room HVACPending · Pending ownership approval
Wine Unit - Ductless SlimlinePending · Pending ownership approval · Approved
Interior PaintingPending · Pending ownership approval
Millwork Installer for Royal LaserPending · Pending ownership approval

Shop Drawings/ Specialty Engineering

Revising Shoe & Glass Rail PackageIn Progress · New plans being issued 4/10-then counter sign & submit · Aarons Eng
Creating engineered shop drawing for elevated condensersIn Progress · Retaining Trio Design to create SK & Provide Letter · Trio
Modifying exterior column framingIn Progress · With bigger frames to go past concrete · Shearwall
Deck design with pedestalsIn Progress · Shearwall

Permits

Shop Drawings/ NOA Needed for Permit for front doorPending
Shop Drawing/NOA for Garage DoorPending
Deck design with pedestalsIn Progress · Shearwall

Inspections

Low VoltagePassed · Maxicon
Windows Buck- AnchoringPassed · Infinite
Roof In ProgressPassed · Bustos
Mechanical RoughPassed · SE Mechanical
Fire Alarm Rough InspectionPassed · Delta Tech
Framing Rough InspectionPassed · Passed except for Staff Area/Service Wing · BRLH
Gas RoughTBD · Pending Approvals on MEP Revision · P&P Plumbing
Electrical RoughPartials · Pending Ground Floor & Garage · Delta Tech
Plumbing Rough (shower pans & insulation to be inspected)TBD · Gym & Master Showerpans/Pipe insulation · P&P Plumbing
Insulation InspectionTBD · To Be scheduled after Icynene & again after exterior walls

Design Items

Architecture

Site plan of marina for easement recording for FPLIn Progress

Structure

Ongoing Review of shop drawings for permitsIn Progress

Paramount

Adjust their recommendations for sconditions in fieldIn Progress

Interior

Master Carpet Specification
FFE Layout with Owner
Fabrics & Veneers Final Schedule
Exterior Ceiling Fans

Lighting

Maxicon adding in missing addresses for the millworkIn Progress · Maxicon

Landscape

Pending new plans from LANDNeed Update · Matt/Land
Landscape LightingNeed Update · Matt/Land?

MEP

Submittal of Hot Water HeaterPending Review · In MEP Court · MEP
Submittal for AC RoomPending Review · In MEP Court · MEP
Submittal for Wine Wall RefrigerationPending Review · In MEP Court · MEP
Narrative to Resolve Revision Denial CommentsNeed Update · Andres working with MEP · MEP
Submittal for Balancing ValvesIn Progress · Broges Reviewing with MEP · MEP
Wellness Equipment ElectricalIn Progress · MEP
Buyouts Section - General to be Sub ContractedStatus · Notes · Contractor
Stair Guard RailIn Progress · New proposal submitted for painted metal finish · Champion
Driveway, Pedestrian, Side Yard Gates, HandrailsIn Progress · Re-pricing · Champion
Wine Room InstallerIn Progress · Submitted Proposal, BRLH to retrieve additional
Water Feature StoneIn Progress · Pending Proposal/ Upgrade Insurance · L-Gant
Stone surround at entryIn Progress · Pending Proposal/ Upgrade Insurance · L-Gant
Deck & Pedestal SystemIn Progress · Tri County Submitted, Pending David Failes · Tri County
Garage DoorsIn Progress · Johns Garage Approved with Vertical Cedar · Johns Garage
Garage Cabinetry & FlooringIn Progress · Proposal to be retrieved · Premier
LandscapingIn Progress · Pending New Plans
Landscape LightingNeed Update · Pending Design
IrrigationIn Progress · Pending New Plans
Shower EnclosuresIn Progress · Pricing
Driveways & WalkwaysIn Progress · Re-pricing, New design with concrete & turf · Miami Crete
Interior PaintingIn Progress · Proposals submitted · Oleg or Harold
New Gym Rubber FlooringIn Progress · Requested pricing from NWF · NWF
Walnut Veneer at Kitchen Island CeilingIn Progress · Requested pricing from Royal Laser · Royal Laser
Wellness EquipmentIn Progress · Requested pricing from Delta Tech · Delta Tech
In floor heating for His & Her Master

Issues to Resolve

Speed of the Car Carousel
Dock DemoPending Proposal & Review Process · Shore
Schedule Critical PathStatus/Date
Completion DateTCO & Move In: · 08/01/2027
CO12/31/2027

▶ PENDING MATERIALS | Long-Lead + Owner Hot Items

HOT ITEM ALEX (OWNER) KEEPS ASKING ABOUT

-powder coated ringlets expected on 5/1

-Target delivery date for millwork Royal (We need to look into phased delivery? Is this practical or even possible?)

HVAC

Diffusers (verify full delivery vs. partial)

Plenum boxes (especially foyer curved diffusers)

Linear slots / specialty ceiling vents

Mini-split units (if any still outstanding)

Grilles and return covers

Electrical

Light fixtures (interior + exterior)

LED step lights (magnetic – per your preference)

Panels / breakers (if revisions still pending approval)

Exterior lighting + landscape lighting

Low-voltage components (cameras, wiring, devices)

Plumbing

Fixtures (toilets, faucets, specialty items)

Water heaters / equipment

Exterior hose bibs / drainage components

Pipe materials for remaining rough/finish

Gas

Propane tank (new installation – critical path)

Gas piping materials (2” high-pressure conversion)

Regulators + fittings

Architectural / Finishes

Interior floor finishes (pending proposal + selection)

Exterior pavers (still needs confirmation)

Stucco materials / finish coats

Paint system (Loxon primer confirmed, but full system?)

Caulking (Powerhouse for finish transitions)

Millwork / Specialty

Wine display systems

Custom cabinetry

Interior doors / hardware

Security doors

Exterior / Site

Fencing (final decision pending)

Mailbox

Irrigation system materials + meter

Landscaping materials (pending plans + mango tree decision)

Structural / Misc

Louvers (awaiting Borges details)

Framing-related specialty items tied to louvers

Glass railings (proposal needs execution)

Water feature materials (black granite revision)

▶ MANPOWER LOG | May 11–18, 2026

✅ DRYWALL SCREW INSPECTION PASSED 5/18 (ENTIRE 2ND FLOOR) | Lujo adding 10 finishers 5/19 | 1F drywall starts 5/19
DateCompany · # Workers · # Hours · Man-Hours · Work Performed / Notes

Monday, May 11, 2026 | 51 workers | 10 trades

05/11/2026Lujo Drywall · 14.0 · 8.0 · 112 · Hanging Drywall / Finishing coves / installing Dorr houzzer Framing Luver area
Bart Reines Luxury Homebuilder6.0 · 8.0 · 48 · - Omar Superintendent - Greeg PM - Labor
Natural Wood Flooring6.0 · 8.0 · 48 · Plywood installation fist floor
Delta Tech5.0 · 8.0 · 40 · Electrical lights panel
Architectural Pre Cast & Foam5.0 · 8.0 · 40 · Foam installation
Dennis Service Corp.5.0 · 8.0 · 40 · Painter
Champion Welding4.0 · 8.0 · 32 · - Shoe inspection Pass. - Rooftop parapet cover replace.
Bozzui3.0 · 8.0 · 24 · T&G kitchen area
Dennis Service Corp.2.0 · 8.0 · 16 · Stucco punch out
Southeast Florida Mechanical1.0 · 8.0 · 8 · Punch out

Tuesday, May 12, 2026 | 55 workers | 11 trades

05/12/2026Lujo Drywall · 15.0 · 8.0 · 120 · - Andras on site most of the day - Hanging Drywall / Finishing coves / - installing Dorr houzzer - Framing Luver area - T&G Riglet installation
Delta Construction Group7.0 · 8.0 · 56 · -Delta tech supervisor Jose was on site most of the day supervising. - Pile installation - Removing forms from the front steps
Bart Reines Luxury Homebuilder6.0 · 8.0 · 48 · - Omar Superintendent - Greeg PM - Labor
Natural Wood Flooring6.0 · 8.0 · 48 · Plywood installation VIP, kids# 2-3
Delta Tech5.0 · 8.0 · 40 · Electrical panel Aron couple hours German most of the day
Architectural Pre Cast & Foam5.0 · 8.0 · 40 · Foam installation
Dennis Service Corp.3.0 · 8.0 · 24 · Painter caulking windows
Bozzui3.0 · 8.0 · 24 · T&G kitchen area
Dennis Service Corp.2.0 · 8.0 · 16 · Stucco punch out
Borges Architects + Associates2.0 · 2.0 · 4 · Andres’s Borges
Southeast Florida Mechanical1.0 · 8.0 · 8 · Punch out

Wednesday, May 13, 2026 | 46 workers | 9 trades

05/13/2026Lujo Drywall · 15.0 · 8.0 · 120 · - Andras on site most of the day - Hanging Drywall / Finishing coves / - installing Dorr houzzer - Framing Luver area - T&G Riglet installation
Bart Reines Luxury Homebuilder6.0 · 8.0 · 48 · - Omar Superintendent - Greeg PM - Labor
Natural Wood Flooring6.0 · 8.0 · 48 · Plywood installation gym wellness
Architectural Pre Cast & Foam5.0 · 8.0 · 40 · Foam installation
Dennis Service Corp.4.0 · 8.0 · 32 · - Removing scaffolding - Punch out
Delta Tech3.0 · 8.0 · 24 · Electrical panels
Bozzui3.0 · 8.0 · 24 · T&G kitchen area
Dennis Service Corp.2.0 · 8.0 · 16 · Painter caulking windows
Delta Construction Group2.0 · 8.0 · 16 · - Removing forms from the front steps

Thursday, May 14, 2026 | 53 workers | 11 trades

05/14/2026Lujo Drywall · 16.0 · 8.0 · 128 · - Hanging Drywall / Finishing coves - installing Dorr houzzer - Framing Luver area - T&G Riglet installation
Bart Reines Luxury Homebuilder6.0 · 8.0 · 48 · - Omar Superintendent - Greeg PM - Labor
Natural Wood Flooring6.0 · 8.0 · 48 · Plywood installation gym wellness
Delta Tech5.0 · 8.0 · 40 · Electrical panels
Architectural Pre Cast & Foam5.0 · 8.0 · 40 · Foam installation
Champion Welding4.0 · 8.0 · 32 · Mainstairs mockup
Dennis Service Corp.3.0 · 8.0 · 24 · - Removing scaffolding - Punch out
Bozzui3.0 · 8.0 · 24 · T&G kitchen area
Dennis Service Corp.2.0 · 8.0 · 16 · Painter caulking windows
JAJ INSULATION CORP.2.0 · 8.0 · 16 · Punch out
Arquitek1.0 · 8.0 · 8 · Bob installing 1/4 Birch plywood

Friday, May 15, 2026 | 56 workers | 11 trades

05/15/2026Lujo Drywall · 16.0 · 8.0 · 128 · - Hanging Drywall / Finishing coves - installing Dorr houzzer - Framing Luver area - T&G Riglet installation
Bart Reines Luxury Homebuilder6.0 · 8.0 · 48 · - Omar Superintendent - Greeg PM - Labor
Natural Wood Flooring6.0 · 8.0 · 48 · Plywood installation gym wellness
Delta Tech5.0 · 8.0 · 40 · Electrical outlets
Architectural Pre Cast & Foam5.0 · 8.0 · 40 · Foam installation
Champion Welding4.0 · 8.0 · 32 · Mainstairs mockup
Flowtech4.0 · 8.0 · 32 · - Installing Jandy panels - water feature relocating waterlines under the finish grade
Dennis Service Corp.3.0 · 8.0 · 24 · Painting metal riglet transitions throughout the knife edge
Dennis Service Corp.3.0 · 8.0 · 24 · - Removing scaffolding - Punch out
Bozzui3.0 · 8.0 · 24 · T&G kitchen area
Arquitek1.0 · 8.0 · 8 · Bob installing 1/4 Birch plywood
Monday, May 18, 2026 | 48 workers | 10 trades ★ DRYWALL SCREW INSPECTION PASSED — 2F COMPLETE
05/18/2026Lujo Drywall · 14.0 · 8.0 · 112 · - Hanging Drywall / Finishing coves - installing Dorr houzzer - Framing Luver area - T&G Riglet installation
Bart Reines Luxury Homebuilder6.0 · 8.0 · 48 · - Omar Superintendent - Greeg PM - Labor
Natural Wood Flooring6.0 · 8.0 · 48 · Plywood installation gym wellness
Delta Tech5.0 · 8.0 · 40 · Electrical
Architectural Pre Cast & Foam5.0 · 8.0 · 40 · Foam installation
Dennis Service Corp.3.0 · 8.0 · 24 · Painting metal riglet transitions throughout the knife edge
Dennis Service Corp.3.0 · 8.0 · 24 · - Removing scaffolding - Punch out
Bozzui3.0 · 8.0 · 24 · T&G máster bedroom patio
Flowtech2.0 · 8.0 · 16 · - Installing Jandy panels - water feature relocating waterlines under the finish grade
Arquitek1.0 · 8.0 · 8 · Bob installing 1/4 Birch plywood door guides

CEM INTELLIGENCE FLAGS — MAY 11–18, 2026

★ MILESTONE✅ DRYWALL SCREW INSPECTION PASSED — ENTIRE 2ND FLOOR — 5/18/2026 · Critical path milestone achieved. Lujo adding 10 finishers 5/19. 1F drywall installation starts 5/19. Backing installation begins on one side throughout entire 1F. Significant manpower increase incoming. This is the project's most important milestone since piles were installed.
✅ POSITIVELujo Drywall — ramping to record levels. 14→16 workers, adding 10 finishers 5/19 · Consistently 14-16 workers across all 6 days. Now expanding to include finishers. Andres on site 5/12 and 5/13. 1F start 5/19 is a major acceleration signal.
✅ POSITIVEChampion Welding — Main Stairs mockup 5/14 and 5/15 · Main stairs mockup underway per OAC3 direction. 4 workers both days. Fabrication scope progressing.
✅ POSITIVEFlowtech — Jandy panels and water feature line relocation (5/15 + 5/18) · Flowtech appeared 5/15 (4 workers) and 5/18 (2 workers) installing Jandy panels and relocating water feature waterlines. Active pool/water feature scope progressing.
✅ POSITIVEArquitek — Bob on site 5/14, 5/15, 5/18 installing door guides · 1 worker installing 1/4 birch plywood door guides. Consistent presence. Interior millwork prep underway.
✅ POSITIVEDelta Construction Group — forms removed from front steps 5/13 · Forms removed from front steps. Structural concrete work progressing. Also supervisory role confirmed.
✅ POSITIVEDennis Service Corp — painting metal riglet transitions at knife edge (5/15 + 5/18) · Riglets being painted at knife edge. Scaffold removal also ongoing. Exterior finishing sequence advancing.
✅ POSITIVEBozzui — expanded to master bedroom patio area 5/18 · Previously T&G kitchen. Now also master bedroom patio. Scope expanding — confirms Bozzui's reliability for broader exterior wood ceiling scope.
🔴 CRITICALP&P Plumbing — ABSENT ALL 6 DAYS (5/11 through 5/18) · Not a single day logged over the full 6-day period. Drywall screw inspection is now passed — ceiling closure sequence is starting. If P&P does not appear to complete and test condensate drains and tub/shower roughs before ceilings close, those items get drywalled in. Demand letter is now urgent at the highest level.
🔴 CRITICALSE Florida Mechanical — 1 person, 2 of 6 days only (5/11 + 5/12), absent 5/13–5/18 · Present only 5/11 and 5/12 for punch out. Completely absent 5/13 through 5/18 — a 6-day consecutive absence during the week ceiling closure begins. HVAC punch list items from the 5/6 walkthrough (bed 1 drain, access panels, VIP filter slot, bed 2 damper racks) are still open. If Gabriel does not clear these before Lujo closes 1F ceilings, they are permanently inaccessible.
📋 NOTEJAJ Insulation Corp — 2 workers 5/14 for punch out · One-time appearance for insulation punch out. Not new scope — cleanup work.
📋 NOTEArquitek — 'Bob' appearing consistently (5/14, 5/15, 5/18) · Not previously in any tracker under this name. Installing 1/4 birch plywood — likely door guide prep work. Confirm sub relationship and whether this is a CO or base scope.

▶ BOARD LOG | 5/13/2026

DONE | NEW | RED = Critical | -> = Reassigned

#Trade · Sub / Vendor · Action Item · Target Date · Status · Priority · Board Change (5/13)
1.0Roofing · Roofing Sub · Scaffolding removal · 5/4-5/5 · DONE · HIGH · CROSSED OUT — done 5/4 or 5/5
2.0Roofing · Campion Welding · Rooftop parapet cap replacement — completed 5/6 · 5/6/2026 · DONE · HIGH · Completed per board + manpower log confirmed
3.0Roofing · Roofing Sub · Overflow scuppers caught back · 5/11/2026 · DONE · HIGH · 'Caught back the overflow scuppers 5/11' on board
4.0Roofing · Roofing Sub · Waterproofing punch out areas · 5/11/2026 · DONE · HIGH · 'Continue waterproofing punch out areas 5/11' on board
5.0Roofing · SE Florida Mechanical · Isolations — Gabriel confirmed done · 5/11/2026 · DONE · HIGH · 'I Gabriel' CROSSED OUT — isolations confirmed complete
6.0Roofing · Dennis Service Corp. · Stucco shoe rooftop · 5/14/2026 · DONE · HIGH · 'Stucco Shoe Rooftop 5/14' noted and crossed
7.0Floor Heating · Vendor · Floor heating material + installation · 4/20/2026 · DONE · HIGH · 'Ordered 4/20/26 Completed' written in RED
8.0Master His-Her · Lujo Drywall · Drywall — all phases (ceiling, walls, hanging, finish) · 4/20-4/27 · DONE · HIGH · All four drywall items checked off on board
9.0Main Stair · Gregg / Metal Fab · Markup meeting — Thursday 5/14 · 5/14/2026 · DONE · HIGH · 'Markup Thursday 5/14' with checkmark on board
10.0Exterior Stone · Michael (CEM) · Liability insurance concluded · 4/29/2026 · DONE · HIGH · 'Michael Done' crossed out in red — confirmed closed
11.0Water Meter · Gregg (reassigned from Michael) · Water meter task — REASSIGNED to Gregg / Teco Gas · TBD · REASSIGNED · HIGH · 'Michael Task' CROSSED OUT in red. 'Gregg Task' written. Teco Gas noted.
12.0FENCE · Borges / Victor · FENCE VE — 'Cluster F*ck — Borges' written in RED · ASAP · Open — Escalating · CRITICAL · RED NEW: Omar flagging coordination breakdown between Borges and Victor on fencing VE revision.
13.0PVC 24in Storm Drain · Chana · 'Its been 4 months — Please lets get this scheduled' — red urgent note · ASAP · Open — Overdue · CRITICAL · RED NEW urgent escalation from Omar. 4 months since last cleaning. Chana to schedule immediately.
14.0HVAC · SE Florida Mechanical · Plenum HOT + Chana Dates? — STILL on board, no resolution · ASAP · Open — No dates · CRITICAL · RED Still 'HOT' and 'Chana Dates?' — unchanged from prior boards despite OAC flags.
15.0Metal Fabricator · Campion Welding · Final Brake Metal — White Facade? (new red item) · ASAP · Open · CRITICAL · RED NEW on board. Facade brake metal color/finish decision still blocking fabrication.
16.0Metal Fabricator · Campion Welding · Laundry Holding Tank Stands (new red item) · ASAP · Open · CRITICAL · RED NEW item not previously in any tracker. Laundry area holding tank stands required.
17.0HVAC · SE Florida Mechanical / David Rogers · ISOLATORS — added to HVAC card · ASAP · Open · HIGH · NEW: 'ISOLATORS' written on HVAC card. Roof HVAC isolator engineering pending.
18.0Wine Cellar · Vendor TBD · Wine cellar delivery dates — 5/10 and 7/1/26 on board · 5/10 / 7/1/26 · Open · HIGH · NEW: Two dates added — 5/10 and 7/1/26. Phased or two separate deliveries?
19.0Gas Meter · Teco Gas / Gregg · Gas meter — Gregg Task + Teco Gas contact noted · TBD · Open · HIGH · NEW: 'Gregg Task' and 'Teco Gas' written on board. Installation date, permit, material needed.
20.0Pile Schedule · Pile Contractor · Pile inspection — MAY 11 date + Installation noted · 5/11/2026 · Scheduled · HIGH · NEW: 'Inspection Date MAY 11' and 'Installation' on board. Gas revision cleared this.
21.0Master His-Her · SDS Stone Int. · Stone delivery date + metal strips. Process: material/layout/cut/install · TBD · Open · CRITICAL · No change — 'Date Starting?' still on board
22.0Master His-Her · Paint Sub · Paint — no owner approvals · TBD · Open · CRITICAL · No change — 'No Approvals' still on board. Interior priming week of 5/18 approved.
23.0Fence · Andres / Victor · Final revision, fabrication, installation dates · TBD · Open · CRITICAL · 'Cluster F*ck — Borges' — see RED item above
24.0Main Stair · ELD / Metal Fab · Final revision, fabrication, installation dates · TBD · Open · HIGH · Markup done 5/14. Dates still TBD.
25.0Paver · Paving Sub · Order material, permit, install date, concrete driveway proposal · TBD · Open · HIGH · No change
26.0Landscaping · Matthew / LAND · Completion plans date, permit, site selection · TBD · Open · HIGH · Matthew on site 5/7. Tree conflict with utilities per OAC3 — walk needed.
27.0Civil · Marco Osorio · Civil revision in progress — received site plan + city comments · 5/20/2026 · In Progress · HIGH · Marco working per OAC3. Follow up 5/20.
28.0Slab · Concrete Sub · Starting date + rebar loop straps + completion · TBD · Open · CRITICAL · No change — follows pile inspection 5/11
29.0PVT Cladding · Vendor · First order, cladding not including front door, job site delivery · TBD · Open · HIGH · No change
30.0PVT Front Door · Vendor · Delivery date · TBD · Open · HIGH · No change
31.0Pool · Pool Sub · Pending revisions? Equipment install? Water feature relocate? · TBD · Open · HIGH · Pool contractor job walk 5/15 per OAC3
32.0T-G Wood Ceiling · Bozzui · Paint Riglet White + T&G kitchen active · 4/21 · In Progress · MED · Bozzui 3 workers daily on T&G kitchen per manpower log
33.0Windows · Infinite Windows — Estevan · Installation date (Sill Ricer proposal done) · TBD · Open · HIGH · Proposal crossed out = resolved. Install date TBD. Note: not to extend up 3/4in
34.0Propane Tank · Surveyor / Vendor · Plans printed big + survey · TBD · Open · MED · No change
35.0Electrical (site) · ELD · Relocate temp power date? · TBD · Open · HIGH · No change
36.0Back Fill · Site Contractor · Date confirmation · TBD · Open · MED · Follows slab
37.0Foam Paneling · SPS — Jennifer · Installation completion · 5/31/2026 · Scheduled · MED · Delivery crossed out (done). Completion 5/31 circled.
38.0AV · MAXICON · Dressing room shade wire, alarm boxes, steam room speaker · TBD · Open · MED · No change
39.0Metal Fab · Campion Welding · AC filter frame patio — completed? Friday check · 5/15/2026 · Open · HIGH · 'Patio completed? Friday' still on board
40.0Omar · Omar Rodriguez · Daily 11am + new red annotations (Argent coordination dates?) · Daily · Ongoing · HIGH · New red annotations visible in Omar's column

▶ BOARD LOG | Prior (4/24)

🟢 = Completed/Crossed out on board | 🆕 = New info | 🔴 = Red ink on board (critical) | ⚠ = Trouble/Escalation
#Trade / Area · Sub / Vendor · Action Item · Target Date · Status · Priority · Board Update (latest photo)
1.0Elevator · Elevator Sub · Shaft painted + permit · 4/18/2026 · ✅ DONE · HIGH · ✅ Board confirmed complete
2.0Master His & Her · Lujo Drywall · Drywall ceiling hang · Mon 4/20 · ✅ DONE · HIGH · ✅ CROSSED OUT on board — completed
3.0Master His & Her · Lujo Drywall · Drywall wall hang · Mon 4/20 · ✅ DONE · HIGH · ✅ CROSSED OUT on board — completed
4.0Master His & Her · Lujo Drywall · Drywall hanging (3 days) · 4/23 · ✅ DONE · HIGH · ✅ CROSSED OUT on board
5.0AV / HVAC · HVAC Contractor · Condensate scope — HVAC owns · Resolved · ✅ DONE · HIGH · ✅ Resolved — HVAC Contractor confirmed
6.0Entrance / Main Stair · ELD Electric · ELD electrical start · 4/28/2026 · ✅ DONE · HIGH · 🆕 Date confirmed: ELD started 4/28
7.0Entrance / Main Stair · ELD Metal Fab · ELD metal fabricator start · 4/27/2026 · ✅ DONE · HIGH · 🆕 Date confirmed: started 4/27
8.0Master His & Her · Vendor TBD · Floor heating — material ordered · 4/21/2026 · ✅ DONE · HIGH · 🆕 'Material Ordered 4/21/26' on board
9.0HVAC · Gabriel (HVAC Sub) · ⚠ Supply duct failure at plenums — demand letter required · IMMEDIATE · Open — Escalating · 🔴 CRITICAL · 🔴 NEW from Omar task list. Ducts coming apart. Demand letter to Gabriel. Escalate to Craig if no response.
10.0Gas / Life Safety · Chana / Engineer · ⚠ Gas revision — walls cannot close until complete · IMMEDIATE · Open — Life Safety Hold · 🔴 CRITICAL · 🔴 NEW life safety item. Cannot close any walls. Required for final sign-off.
11.0Gas / Electrical · Herman (Electric) · ⚠ Underground electrical conflict with gas lines — CO pending · ~3 weeks · Pending CO · 🔴 CRITICAL · 🔴 NEW. CO from Herman ~3 weeks. Must be approved before relocation can proceed.
12.0Master His & Her · SDS Stone / Sergio AFS · His & Hers stone — delivery schedule to fabricator · ASAP · Open — No dates · 🔴 CRITICAL · 🔴 Backing date + vanity L-angles still red on board. SDS process: Material→Layout→Cut→Install
13.0Electrical — 1st Floor · ELD / Campion · First floor electrical completion — date required · ASAP · Open · 🔴 CRITICAL · 🆕 ELD started 4/28. Completion date still needed. Revised lighting + relocations included.
14.0Front Facade · Foam Panel Sub · Fluted foam panels — stone vs. painted DECISION NEEDED · IMMEDIATE · Open — Owner Decision · 🔴 CRITICAL · 🔴 NEW. Panels being installed NOW. Must confirm finish immediately or work stops.
15.0HVAC — Master Wing · HVAC Sub · Final decision + owner approval for master wing HVAC · ASAP · Open · 🟠 HIGH · 🆕 Plenum still flagged 'Hot' + 'Chana Dates?' on board. Master hallway + gym.
16.0Exterior Wood Ceiling · Sub TBD · Paint Riglet White · 4/21 · Open · HIGH · Riglets powder coating Wednesday per task list
17.0Pool Equipment · Pool Sub · Release pool equipment to sub — start work · ASAP · Open · 🟠 HIGH · 🆕 Pool pedestals + deck shop dwgs + fire pit shop dwgs all pending
18.0Transformer / Marina · Utility / Marina · Finalize pedestals + relocation · TBD · Open · 🟠 HIGH · 🆕 NEW from task list
19.0Steam Room · MAXICON · Finalize lighting + confirm with ownership · TBD · Open · 🟠 HIGH · Coordinate with MAXICON speaker install
20.0Garage Doors · Vendor TBD · Release for production · ASAP · Open · 🟠 HIGH · 🆕 NEW from task list — ready to release
21.0Spiral Stair & Railings · Metal Fab / TBD · Release scope + begin coordination + install · TBD · Open · 🟠 HIGH · 🆕 NEW from task list. Coordinate with Campion Welding.
22.0Metal Fabricator · Campion Welding · LED metal strip — galvanize (DEADLINE 4/29) · 4/29/2026 · Open — URGENT · 🔴 CRITICAL · 🔴 DEADLINE TODAY per task list. Approved on site.
23.0Metal Fabricator · Campion Welding · Riglets T&G — powder coating · Wednesday · Open · 🟠 HIGH · 🆕 Due Wednesday
24.0Roof · Metal Fab / Roofing · Metal equipment enclosure — shop dwgs → fab → install · TBD · Open · 🟠 HIGH · 🆕 NEW from task list
25.0Garage · HVAC Sub · Garage A/C relocation — update plans · TBD · Open · 🟠 HIGH · 🆕 NEW from task list
26.0Retaining Wall · Civil / Public Works · Finalize retaining wall solution · TBD · Open · 🟠 HIGH · 🆕 NEW from task list
27.0Pavers / Driveways · Paving Sub · Finalize + start · TBD · Open · 🟠 HIGH · 🆕 NEW from task list
28.0Civil · Civil Engineer · French drain relocation · Thursday 4/30 · Scheduled · 🟠 HIGH · 🆕 Scheduled Thursday per task list — check required
29.0Civil · City / Plumber · Pipe work (City) — clean pipe, no lining · TBD · Open · 🟠 HIGH · 🆕 NEW from task list
30.0Propane · Vendor / Surveyor · Gas tank coordination + survey · TBD · Open · MED · After scaffolding removed
31.0Propane Tank Delivery · Vendor · Delivery date confirmation · TBD · Open · MED · No change
32.0Slab · Concrete Sub · Start date + rebar loop straps + completion · TBD · Open · 🔴 CRITICAL · Still TBD — feeds drywall + framing inspection
33.0Pile Schedule · Pile Contractor · Inspection + 10-day mobilization lead · TBD · Open · 🔴 CRITICAL · Must precede slab start
34.0Electrical (Site) · Electrician · Relocate temp power · TBD · Open · HIGH · Unchanged
35.0Back Fill · Site Contractor · Date confirmation · TBD · Open · MED · Follows slab
36.0Interior Painting · Paint Sub · Revise + resend proposal · ASAP · Open · 🟠 HIGH · 🆕 From task list. Paint approvals from owner still 'No Approvals' — escalate simultaneously.
37.0Exterior Painting · Paint Sub · New proposal — 25% darker color · ASAP · Open · 🟠 HIGH · 🆕 NEW. Owner wants 25% darker. Confirm color selection first.
38.0AV · Chana / AV Sub · AV Change Order — confirm + process · TBD · Open · 🟠 HIGH · Still flagged on board
39.0Stucco · Dennis Service Corp · Chana's proposal to Dennis · TBD · Open · 🟠 HIGH · Stucco started 4/21 — confirm proposal sent
40.0Windows · Infinite Windows — Estevan · Sill Ricer proposal + install date · TBD · Open · 🟠 HIGH · No change
41.0Finish Flooring · AnBos Corp · Sill Ricer proposal + install date · TBD · Open · MED · No change
42.0Architect · Borges — Reinaldo AOR · Prado Outlets proposal + NWF owner contact · TBD · Open · MED · No change
43.0Foam Paneling · SPS — Jennifer · Installation completion · 5/31/2026 · Scheduled · MED · Delivery 4/27, start 4/27, complete 5/31
44.0Royal Laser · June Glamm (contact) · Date — June 2026 timeframe · June 2026 · Open · MED · Contact: June Glamm
45.0Master His & Her · Paint Sub · Paint — master suites (NO OWNER APPROVALS) · TBD · Open — Blocked · 🔴 CRITICAL · 🔴 Red on board: 'No Approvals' from owner. Blocks all painting. Escalate immediately.
46.0Master His & Her · Maxicon (unconfirmed) · Electrical fixtures — Maxicon PROBABLY (not confirmed) · TBD · Open — Unassigned · 🟠 HIGH · 🔴 'Maxicon Probably' — sub not confirmed. Must assign formally.
47.0Plumbing — Scope Q · Power Plumbing / HVAC · Who insulates condensing lines? Horizontal = TBD · ASAP · Open — Scope Gap · 🔴 CRITICAL · 🔴 'Chana?' on board. Vertical=HVAC confirmed. Horizontal unassigned. Fails inspection if unresolved.
48.0MAXICON · MAXICON · Shade wire (dressing room) + alarm boxes + steam room speaker · TBD · Open · MED · No change
49.0Turntable · Carousel USA / Rubicon · Proposal to Alex — Rubicon to install metal guide · TBD · Open · MED · No change
50.0Omar — Coverage · Chana / Gregg Covine · Daily 11AM field check-in (Omar in recovery) · Daily · Ongoing · 🔴 CRITICAL · Gregg Covine now added as lead PM
Crowncore
Construction Management  ·  Confidential project data  ·  Generated from 186 Bal Bay Master Tracker v10